MS6-M26001 - 2026 Street Maintenance - Phase 1

Project Information

Bid Title
MS6-M26001 - 2026 Street Maintenance - Phase 1
Issuing Agency
City of Lawrence
Location
Kansas
Published Date
Jan 14, 2026
Closing Date
Feb 3, 2026
Government Level
State & Local
Status
Closed
Original Source
Join to Access Full Details
Project Description


Project ID:

Title: MS6-M26001 - 2026 Street Maintenance - Phase 1

Addenda: 0

Release Date: 1/14/2026

Due Date: 2/3/2026

Follow
MS6-M26001 - 2026 Street Maintenance - Phase 1
Invitation For Bid
MSO - CMED
91350 , 91384 , 91395 , 91396 , 96861
Project ID: CIFB-2600001
Release Date: Wednesday, January 14, 2026
· Due Date: Tuesday, February 3, 2026 3:30pm
Posted Wednesday, January 14, 2026 8:00am
All dates & times in Central Time
Draft Response No Bid19 days, 19 hours, 53 minutes


Post Information

Posted At:Wed, Jan 14, 2026 8:00 AM
Sealed Bid Process:Yes (Bids Sealed / Pricing Sealed)
Private Bid:No
Overview


Summary

The work to be done under this contract includes: Mill and overlay, microsurfacing, and pavement patching
across the City of Lawrence. The project also includes sidewalk ramps and minimal concrete pavement
replacements. The project includes, but is not limited to the following approximate quantities of work: 10,844
SY of milling, 1,518 tons of asphalt surface course (2”), 108,003 SY of microsurfacing, 3,700 LF of curb and
gutter, 321 SY of concrete pavement, 724 SY of sidewalk, and 3,789 SF of sidewalk ramps.

Schedule:
Area 1(location on title page of construction plans)- No schedule restrictions. The area may be worked on
concurrently with other project locations.
Area 2 (location on title page of construction plans)2- Contractor Shall start after July 15, 2026 and needs to be
coordinated with "MS-230027 - Maple Lane Storm, Sanitary and Watermain Improvements" project for traffic
control impacts/detour routing likely anticipated work on 19th Street between Maple Lane and Harper Street as
part of that project. Harper Street work may not conflict with the Douglas County Fair (Approximately July 27,
2026 - August 2, 2026) and can start after the fair.
Area 3 (location on title sheet of construction plans)- No schedule restrictions. The area may be worked on
concurrently with other project locations.



Timeline

Release Project Date:
January 14, 2026
Question Submission Deadline:
January 23, 2026, 12:00pm
Response Submission Deadline:
February 3, 2026, 3:30pm
* Disclaimer: Government BidHub provides information on bids, RFPs (Requests for Proposals), and RFQs (Requests for Qualifications) solely for convenience and informational purposes. This site is not an official public notice board. For official details, responses, or inquiries, please contact the relevant government agency directly.

Government Bids

Empower Your Bidding Strategy

Unlock Government BidHub's unparalleled access to high-quality, tailored bid information.

  • Access an extensive database of bids, including comprehensive local and state opportunities.
  • Receive customized alerts for the bids that matter most to your business.
  • Explore detailed specifications to ensure precise and competitive submissions.
  • Gain a competitive edge with up-to-date information and exclusive opportunities.

See Also

KSU26-134 - Policy Management...

Bid Name Bid Status Bid Closing Date KSU26-134 - Policy Management SaaS Solution

Kansas University

Bid Due: 7/13/2026

KSU26-134 - Policy Management...

Bid Name Bid Status Bid Closing Date KSU26-134 - Policy Management SaaS Solution

Kansas University

Bid Due: 7/08/2026