MS6-M26001 - 2026 Street Maintenance - Phase 1
Project Information
- Bid Title
- MS6-M26001 - 2026 Street Maintenance - Phase 1
- Issuing Agency
- City of Lawrence
- Location
- Kansas
- Published Date
- Jan 14, 2026
- Closing Date
- Feb 3, 2026
- Government Level
- State & Local
- Status
- Closed
- Original Source
- Join to Access Full Details
- Bid Inquiries
- Join to Access Full Details
- Bid Documents
- Join to Access Full Details
- Project Description
-
Project ID:
Title: MS6-M26001 - 2026 Street Maintenance - Phase 1
Addenda: 0
Release Date: 1/14/2026
Due Date: 2/3/2026
MS6-M26001 - 2026 Street Maintenance - Phase 1FollowInvitation For BidMSO - CMED91350 , 91384 , 91395 , 91396 , 96861Project ID: CIFB-2600001Release Date: Wednesday, January 14, 2026· Due Date: Tuesday, February 3, 2026 3:30pmPosted Wednesday, January 14, 2026 8:00amAll dates & times in Central TimeDraft Response No Bid19 days, 19 hours, 53 minutesOverview
Post Information
Posted At:Wed, Jan 14, 2026 8:00 AM
Sealed Bid Process:Yes (Bids Sealed / Pricing Sealed)
Private Bid:No
SummaryThe work to be done under this contract includes: Mill and overlay, microsurfacing, and pavement patching
across the City of Lawrence. The project also includes sidewalk ramps and minimal concrete pavement
replacements. The project includes, but is not limited to the following approximate quantities of work: 10,844
SY of milling, 1,518 tons of asphalt surface course (2”), 108,003 SY of microsurfacing, 3,700 LF of curb and
gutter, 321 SY of concrete pavement, 724 SY of sidewalk, and 3,789 SF of sidewalk ramps.
Schedule:
Area 1(location on title page of construction plans)- No schedule restrictions. The area may be worked on
concurrently with other project locations.
Area 2 (location on title page of construction plans)2- Contractor Shall start after July 15, 2026 and needs to be
coordinated with "MS-230027 - Maple Lane Storm, Sanitary and Watermain Improvements" project for traffic
control impacts/detour routing likely anticipated work on 19th Street between Maple Lane and Harper Street as
part of that project. Harper Street work may not conflict with the Douglas County Fair (Approximately July 27,
2026 - August 2, 2026) and can start after the fair.
Area 3 (location on title sheet of construction plans)- No schedule restrictions. The area may be worked on
concurrently with other project locations.
Timeline
Release Project Date:January 14, 2026Question Submission Deadline:January 23, 2026, 12:00pmResponse Submission Deadline:February 3, 2026, 3:30pm
Empower Your Bidding Strategy
Unlock Government BidHub's unparalleled access to high-quality, tailored bid information.
- Access an extensive database of bids, including comprehensive local and state opportunities.
- Receive customized alerts for the bids that matter most to your business.
- Explore detailed specifications to ensure precise and competitive submissions.
- Gain a competitive edge with up-to-date information and exclusive opportunities.
See Also
KSU26-134 - Policy Management...
Bid Name Bid Status Bid Closing Date KSU26-134 - Policy Management SaaS Solution
Kansas University
Bid Due: 7/13/2026
KSU26-134 - Policy Management...
Bid Name Bid Status Bid Closing Date KSU26-134 - Policy Management SaaS Solution
Kansas University
Bid Due: 7/08/2026