Tom Adams Bridge Structural Repairs
Project Information
- Bid Title
- Tom Adams Bridge Structural Repairs
- Issuing Agency
- Charlotte County
- Location
- Florida
- Published Date
- Apr 17, 2026
- Closing Date
- Apr 29, 2026
- Government Level
- State & Local
- Status
- Closed
- Ref. #
- 26-369
- Original Source
- Join to Access Full Details
- Bid Inquiries
- Join to Access Full Details
- Bid Documents
- Join to Access Full Details
- Project Description
-
File No:
26-369
Description:
Tom Adams Bridge Structural Repairs
Contact:
stacey.trowbridge@charlottecountyfl.gov
File number:
20260369
Due Date:4/29/2026 2:00:00 PMNotice:Package:Registered Vendors Notified:Presubmittal Sign-in:Tabulation:Recommendation:Commodity Codes:
91300, 91313, 91366, 95900, 95935, 95990
- Attachment Preview
-
COUNTY OF CHARLOTTEPURCHASING DIVISIONCharlotte County Administration Center18500 Murdock CirclePort Charlotte, Florida 33948-1094(941) 743-1378TO:PROSPECTIVE BIDDERSDATE:APRIL 17, 2026RE:ADDENDUM #5 - BID NO. 20260369 – TOM ADAMS BRIDGE STRUCTURAL REPAIRSBID OPENING DATE: 2:00 p.m. (EST) APRIL 29, 2026Bidders are hereby notified that this Addendum shall be made a part of the documents. The intent is to add to, modify, orclarify the documents. Should any of these items have an effect on price, such changes shall be included in the price bid.These items have the same force and effect as if contained in the original.ITEM 1:QUESTION/ANSWERQ1. Per As-builts, Genset being replaced was relocated to Tender House when built. Can we find out whatbrand/model number that genset is?A1. The engine is a John Deere Model 4045HF285H,I,J Power: 94-118 kW @ 1800 RPM. The Alternator was manufacturedby Baldor. Pictures are available, if needed.Q2. For Amendment #4, A1: We still have some concerns about the “LS” pay item. Usually, this pay item is builtin “Linear Feet”. Please note some of the factors we are looking for:PILE JACKETS:• TYPE (structural, non-structural, cathodic)• OLD PILE JACKET REMOVAL: There is mention that there may be existing jackets on these piles. We don’tknow which ones need to be removed, or not.• Annulus space: EORs usually determine the space of concrete filler between the existing and the newfiberglass jacket. This can change the size of the new pile jacket and change the quantity of concrete fill.• Number of Piles that need jackets. Although traditionally this is measured in vertical “linear feet” per pile,we also need to determine how many of the 68 piles will need new pile jackets, etc.• CATHODIC PILE JACKETS vs NON-CATHODIC PILE JACKETS - Cathodic pile jackets usually include somesort of sacrificial zinc mesh, and/or anode. It also requires an Engineer to check if the system is workingproperly in the field once installed.• Pile jackets usually extend past any visual spall/cracks in the pile which could be beyond the marine growthin either direction of the pile.These are all factors above that will make it very hard for us to bid this bid item against our competitors, as nobodyknows exactly the true LF, count, existing pile jackets that need to be removed, and how many piles need pilejackets.Here are some examples of FDOT Pay Items regarding jackets for examples:• 4572121: Cathodic PROTECTION INTERGRAL PILE JACKET, NON-STRUCTRUAL, 16.1-30” GALVANICSYSTEM in LF.• 457112: STANDARD INTEGRAL PILE JACKET, NON-STRUCTURAL, 16.1 to 30” in LF.• 457122: STANDARD INTEGRAL PILE JACKET, STRUCTURAL, 16.1 to 30” in LF.Maybe this feedback can help develop a way that us and our competitors can quote apples to apples?A2. Answers are below:• TYPE is cathodic.• OLD PILE JACKET REMOVAL - All 68 piles have cathodic jackets, refer to 2024 Underwater Inspection Reportfor details of deficiencies.• Annulus space - N/A• Number of Piles that need jackets - Refer to 2024 Underwater Inspection Report for details of deficiencies.Confirm with inspection per Scope Item 14.• CATHODIC PILE JACKETS - Correct, anode to be inspected during underwater inspection per Scope Item 14.• Pile jackets usually extend past any visual spall/cracks in the pile which could be beyond the marine growth ineither direction of the pile. - Per 2024 Underwater Inspection Report, pile jackets extend 12”-24” below marinegrowth.• Refer to scope item 14 on plan sheet B1-07 for work related to pay item 457-70-99, which includes performingunderwater inspection of all pile jackets including cathodic protection system, providing report including estimatedremaining amount of anode and design and repair pile jacket deficiencies. Refer to 2024 Underwater InspectionReport for details of deficiencies.Q3. For Amendment #4, A2: Please clarify, as the recommendation is a color, as opposed to a specific product.A3. For Pay Item 400-150, Cleaning and Sealing Existing Concrete Surface, recommended product to be used is Tex-CoteAnti-Graffiti Coating – Graffiti Guard IV Low Luster Pigmented.Q4. We are hoping to be able to visit the tender house, so we can go inside and visually inspect the conditions andthe existing generator, existing exhaust system, etc. Please advise if this is possible?A4. No, this will not be possible.Q5. Per the Spec’s TS-15 “fuel tank shall be sized to provide 48 hours of run time at full (rated) load.” Is that basedon the generator having to run non-stop for 48-hours? If so, that would mean that this size generator would requirea 500-gallon fuel tank. What size of tank is currently in place?A5. A diesel fuel tank size of 300 gallons is sufficient.Q6. On Sheets B1-07 and B1-20, it mentions an Underwater 2024 report. Can you make this item available?A6. After further consideration, the 6-page Underwater 2024 report is attached.Q7. Should the generator be black iron or cast-iron pipe?A7. Use black iron pipe to match existing condition.Q8. On Sheet B-1-20, regarding navigational lights, is it just 2 lights or all 6?A8. 2 lights, for locations please refer to plan sheet B1-20.Q9. Are there set times or set days for lane closures?A9. No. This can be discussed during the Pre-Con meeting.ITEM 2:DELETION/ADDITION:DELETE: Please delete SP-10 LIQUIDATED DAMAGES, on pages 23-24 from bid package.ADDITION: Please add the following in its place:SP-10 LIQUIDATED DAMAGES: The work shall be completed in 120 calendar days. The contract time shall include thepreparation, submittal, review and approval of submittals, delivery of components and materials, construction, erection,assembly, adjustment, and placement into service for beneficial use of all facilities covered under this contract.Charlotte County shall issue a Notice of Substantial Completion to the Contractor when it has determined that the workidentified in the Contract has been substantially completed and that the facility is operating satisfactorily. Charlotte Countyshall provide the Contractor with a punch list within 14 calendar days after the Notice of Substantial Completion is issued.The punch list will identify the remaining items that must be addressed to the satisfaction of Charlotte County by theContractor to meet his obligations under the Contract. The Contractor shall complete the items on the punch list to thesatisfaction of Charlotte County within 30 additional calendar days of the issuance of the Final Punch List or Notice ofSubstantial Completion whichever is later and prior to the submittal of the application for final payment. Any costs incurredby the County (i.e. inspection time) after the 30- calendar day period shall be charged to the Contractor.The County and the Contractor hereby agree that time is of the essence on this Contract and the County will suffer damagesif the work is not substantially completed within the Contract Time, plus any extensions thereof allowed by Change Order.The County and the Contractor agree that the damages arising out of the breach will include those damages sustained byCharlotte County, its citizens, and the traveling public. The County and Contractor agree that damages arising from thespecified breach will be difficult if not impossible to estimate accurately. The County and Contractor agree that the damagesshall be substantially similar to those damages calculated by the Florida Department of Transportation ("FDOT") pursuantto Florida Statute Section 337 .18 in determining its liquidated damages schedule for projects of similar contract amounts.As such, The County and the Contractor agree that this contract shall adopt FDOT's "Daily Charge per Calendar Day amountof $1,690, as the daily liquidated damage amount should the Project not be substantially completed within the Contracttime. The County and the Contractor further agree that this amount is a reasonable daily amount reflecting default damagesto the County and its citizens should the work not be substantially completed within the Contract time. Further, the Countyand the Contractor agree that the liquidated damages amount listed in this section is intended strictly as compensation fordamages and not as a penalty to secure performance. The County reserves the right to withhold the total amount of theliquidated damages from any payment should the total amount of the liquidated damages exceed the total amount ofretainage at any time.This addendum is binding and is to be considered as if contained within the original bid documents of Bid No. 20260369.Bidders are required to acknowledge receipt of this addendum on their bid forms.Kimberly A. Corbett, C.P.M., CPPBSenior Division Manager-PurchasingKAC/st
- Commodity Codes
-
- NAICS 237310Highway, Street, and Bridge Construction
* Disclaimer: Government BidHub provides information on bids, RFPs (Requests for Proposals), and RFQs (Requests for Qualifications) solely for convenience and informational purposes. This site is not an official public notice board. For official details, responses, or inquiries, please contact the relevant government agency directly.
Empower Your Bidding Strategy
Unlock Government BidHub's unparalleled access to high-quality, tailored bid information.
- Access an extensive database of bids, including comprehensive local and state opportunities.
- Receive customized alerts for the bids that matter most to your business.
- Explore detailed specifications to ensure precise and competitive submissions.
- Gain a competitive edge with up-to-date information and exclusive opportunities.
See Also
BID 25-26-12 51ST YEAR CDBG D...
SOLICITATION DOCUMENTS: BID 25-26-12 51ST YEAR CDBG DRAINAGE IMPROVEMENTS EXHIBIT A - BID
City of Hanllandale Beach
Bid Due: 7/16/2026
Florida National Cemetery, Na...
Follow Florida National Cemetery, National Shrine Turfgrass Renovation Project Active Contract Opportunity Notice
VETERANS AFFAIRS, DEPARTMENT OF