ITB WWTP Influent Pump Station Rehabilitation

Project Information

Bid Title
ITB WWTP Influent Pump Station Rehabilitation
Issuing Agency
City of Port Townsend, WA
Location
Washington
Published Date
Dec 2, 2025
Closing Date
Dec 18, 2025
Government Level
State & Local
Status
Closed
Original Source
Join to Access Full Details
Project Description
ITB WWTP Influent Pump Station Rehabilitation
Bid/RFP Status:
Open - accepting bids and proposals
Bid/RFP Due Date:
Thursday, December 18, 2025 - 2:00pm

Invitation to Bid

Notice is hereby given that sealed bids will be received by the City of Port Townsend, Washington, for WWTP INFLUENT PUMP STATION REHABILITATION up to the hour of 2:00 p.m., Pacific Local Time, Thursday, December 18, 2025, and will be publicly opened and read aloud at that time on the same day in the Port Townsend City Hall, 250 Madison St, Suite 1, Port Townsend, Washington in the second-floor conference room.

An optional pre-bid meeting is to be held at 1:00 PM, local time, on Wednesday, December 10, 2025 at the Wastewater Treatment Plant, 5300 Kuhn St. Port Townsend, WA. Interested prime contractors are encouraged to attend. At this meeting questions concerning the Contract Documents and the proposed work will be discussed.

Summary of Project

This Contract includes, but is not limited to, the following work: Rehabilitation of the WWTP Influent Pump Station wet well, including surface prep and coating, replacement of pump discharge piping and controls, replacement of influent manhole, bypass pumping, electrical upgrades, odor control ducting and fan replacement, and other work, all in accordance with the attached Contract Plans, these Contract Provisions, and the Standard Specifications.

The Engineer’s Estimate is $1,500,000

Plans, specifications, addenda, and plan holders list for this project will be available on-line at www.wilsonengineering.com .

The City intends to award the contract in January 2026 and issue the Notice to Proceed for all work in January 2026. In addition, bypassing of the influent pump station will ONLY be allowed between July 1, 2026 and August 31, 2026. The Contract Work shall be Substantially Complete within 177 Working Days from the Notice to Proceed with Final Completion within 200 Working Days from the Notice to Proceed.

Title VI Statement

The City of Port Townsend, in accordance with the provisions of Title VI of the Civil Rights Act of 1964 (78 Stat. 252, 42 U.S.C. 2000d to 2000d-4) and associated Regulations, hereby notifies all bidders that it will affirmatively ensure that in any contract entered into pursuant to this advertisement, disadvantaged business enterprises will be afforded full and fair opportunity to submit bids in response to this invitation and will not be discriminated against on the grounds of race, color, or national origin in consideration for an award.

City Contact
Questions regarding this ITB may be directed to:
Andre Harper
aharper@cityofpt.us , (360) 379-5088

Attachment Preview
SECTION 00 11 16 - INVITATION TO BID (ITB):
WWTP INFLUENT PUMP STATION REHABILITATION
Invitation to Bid Information:
Submit Bids to:
Date Issued: Wednesday, December 3, 2025
Contact Person: Andre Harper
Email Address: aharper@cityofpt.us
Contact Phone: 360-379-5088
Project Manager: Andre Harper
For delivery in person, or by mail*
Attn: Public Works
Port Townsend City Hall
250 Madison St, Suite 1
Port Townsend, WA 98368
Engineer’s Estimate: $1,500,000
Pre-Bid Meeting (Optional): Wednesday, December 10,
2025
Bid Opening: Thursday, December 18, 2025
*Please refer to Section A: Instructions to
Bidders, Submittal Instructions for further
information on bid submittals
WWTP INFLUENT PUMP STATION REHABILITATION 00 11 16
CITY OF PORT TOWNSEND
INVITATION TO BID
PAGE 1 OF 2
INVITATION TO BID
Notice is hereby given that sealed bids will be received by the City of Port Townsend, Washington, for
WWTP INFLUENT PUMP STATION REHABILITATION up to the hour of 2:00 p.m., Pacific Local
Time, Thursday, December 18, 2025, and will be publicly opened and read aloud at that time on the same
day in the Port Townsend City Hall, 250 Madison St, Suite 1, Port Townsend, Washington in the second-
floor conference room.
An optional pre-bid meeting is to be held at 1:00 PM, local time, on Wednesday, December 10, 2025 at
the Wastewater Treatment Plant, 5300 Kuhn St. Port Townsend, WA. Interested prime contractors are
encouraged to attend. At this meeting questions concerning the Contract Documents and the proposed
work will be discussed.
This Contract includes, but is not limited to, the following work: Rehabilitation of the WWTP Influent
Pump Station wet well, including surface prep and coating, replacement of pump discharge piping and
controls, replacement of influent manhole, bypass pumping, electrical upgrades, odor control ducting and
fan replacement, and other work, all in accordance with the attached Contract Plans, these Contract
Provisions, and the Standard Specifications.
The Engineer’s Estimate is $1,500,000
Plans, specifications, addenda, and plan holders list for this project will be available on-line at
www.wilsonengineering.com.
The City intends to award the contract in January 2026 and issue the Notice to Proceed for all work in
January 2026. In addition, bypassing of the influent pump station will ONLY be allowed between
July 1, 2026 and August 31, 2026. The Contract Work shall be Substantially Complete within 177
Working Days from the Notice to Proceed with Final Completion within 200 Working Days from the
Notice to Proceed.
The City of Port Townsend, in accordance with the provisions of Title VI of the Civil Rights Act of 1964
(78 Stat. 252, 42 U.S.C. 2000d to 2000d-4) and associated Regulations, hereby notifies all bidders that it
will affirmatively ensure that in any contract entered into pursuant to this advertisement, disadvantaged
business enterprises will be afforded full and fair opportunity to submit bids in response to this invitation
and will not be discriminated against on the grounds of race, color, or national origin in consideration for
an award.
_____________________________
Andre Harper, Project Manager
John Mauro, City Manager
***END OF SECTION***
WWTP INFLUENT PUMP STATION REHABILITATION 00 11 16
CITY OF PORT TOWNSEND
INVITATION TO BID
PAGE 2 OF 2
Commodity Codes
  • NAICS 237110Water and Sewer Line and Related Structures Construction
  • NAICS 237990Other Heavy and Civil Engineering Construction
* Disclaimer: Government BidHub provides information on bids, RFPs (Requests for Proposals), and RFQs (Requests for Qualifications) solely for convenience and informational purposes. This site is not an official public notice board. For official details, responses, or inquiries, please contact the relevant government agency directly.

Government Bids

Empower Your Bidding Strategy

Unlock Government BidHub's unparalleled access to high-quality, tailored bid information.

  • Access an extensive database of bids, including comprehensive local and state opportunities.
  • Receive customized alerts for the bids that matter most to your business.
  • Explore detailed specifications to ensure precise and competitive submissions.
  • Gain a competitive edge with up-to-date information and exclusive opportunities.

See Also

BID - SVC - Old Main Sewer Re...

Project: BID - SVC - Old Main Sewer Replacement - Skagit Valley College

State Government of Washington

Bid Due: 7/23/2026

BID - SVC - MV Campus - Aspha...

Project: BID - SVC - MV Campus - Asphalt Repair and Re-striping -

State Government of Washington

Bid Due: 7/09/2026