RFP for CSAH 96 (Dellwood Road) Improvement Project

Project Information

Bid Title
RFP for CSAH 96 (Dellwood Road) Improvement Project
Issuing Agency
Washington County
Location
Minnesota
Published Date
May 22, 2026
Closing Date
Jun 19, 2026
Government Level
State & Local
Status
Closed
Original Source
Join to Access Full Details
Project Description
Bid Title: RFP for CSAH 96 (Dellwood Road) Improvement Project
Category: Washington County Public Works
Status: Open
Description:

The Washington County Public Works Department is issuing this request for proposals (RFP) to provide project coordination, preliminary engineering, final design, stakeholder and public engagement, utility coordination and environmental documentation for the County State Aid Highway (CSAH) 96 (Dellwood Rd.) Improvement Project.

Publication Date/Time:
5/22/2026 8:00 AM
Closing Date/Time:
6/19/2026 3:00 PM
Contact Person:
Mike Kline, EIT – Project Manager
michael.kline@washingtoncountymn.gov
Related Documents:
Attachment Preview
Request for Proposals (RFP) for
PROJECT COORDINATION, PRELIMINARY ENGINEERING, FINAL
DESIGN, STAKEHOLDER AND PUBLIC ENGAGEMENT, UTILITY
COORDINATION, ENVIRONMENTAL DOCUMENTATION
CSAH 96 (Dellwood Rd.)
Improvement Project
City of Stillwater, Grant, Dellwood and Stillwater Township
RFP release date: 05/22/2026
Submission due date: 06/19/2026
Government Center | 14949 62nd Street North | P. O. Box 6 | Stillwater, MN 55082-0006
P: 651-430-6001 | F: 651-430-6017 | TTY: 651-430-6246
www.washingtoncountymn.gov
Washington County is an equal opportunity organization and employer
Table of Contents
1. Introduction ......................................................................................................................................................... 3
1.1. Background Information .............................................................................................................................. 3
1.2. Project Goals and Objectives ....................................................................................................................... 3
1.3. Project Schedule .......................................................................................................................................... 4
2. Scope of Work and Deliverables .......................................................................................................................... 4
2.1. Project Management ................................................................................................................................... 5
2.2. Data Collection and Site Visit ....................................................................................................................... 5
2.3. Public and Agency Engagement................................................................................................................... 5
2.4. Environmental Documentation ................................................................................................................... 6
2.5. Design Services ............................................................................................................................................ 6
2.6. Deliverables ................................................................................................................................................. 9
2.7. Bidding and Construction Assistance Services............................................................................................. 9
2.8. Additional Tasks ........................................................................................................................................... 9
3. Proposal Content ................................................................................................................................................. 9
4. Proposal Submittal............................................................................................................................................. 11
5. Proposal Evaluation ........................................................................................................................................... 11
5.1. Reserved Rights.......................................................................................................................................... 11
6. Proposal Questions ............................................................................................................................................ 11
Page|2
CSAH 96 Improvement Project
1. Introduction
1.1. Background Information
The Washington County Public Works Department is issuing this request for proposals (RFP) to provide
project coordination, preliminary engineering, final design, stakeholder and public engagement, utility
coordination and environmental documentation for the County State Aid Highway (CSAH) 96
(Dellwood Rd.) Improvement Project.
In 2023, the Washington County Board of Commissioners approved the ownership and transfer of a
nine-mile segment of TH 96 from MnDOT. CSAH 96 extends approximately 9 miles from Trunk
Highway 244 to Trunk Highway 95 (St. Croix Scenic Bywy). The corridor functions as a two-lane, rural
undivided roadway and carries an average daily traffic volume of 4,000 to 6,000 vehicles per day. The
posted speed limit is 45 miles per hour west of CSAH 15 (Manning Ave.) and 55 miles per hour east of
CSAH 15 (Manning Ave.). The project corridor is located entirely within the City of Stillwater, Grant,
Dellwood and Stillwater Township.
Washington County, through its Capital Improvement Plan (CIP), has identified this project as Project
No. RB-2693. The anticipated project schedule includes preliminary design in 2026, final design and
right-of-way acquisition in 2027, and construction in 2028. Funding for the project is expected to
include Turnback – Fund Balance and Transportation Advancement Account (TAA) – Safety and Trails.
The project will be delivered as a cooperative effort between Washington County, the City of
Stillwater, Grant, Dellwood, Stillwater Township, Brown’s Creek, Rice Creek and Carnelian-Marine-St.
Croix Watershed Districts, with Washington County serving as the lead agency. All work performed
under the anticipated contract shall comply with applicable procedures, standards, and regulatory
requirements of the Minnesota Department of Transportation (MnDOT), MnDOT State Aid, the
Minnesota Department of Natural Resources (MnDNR), the United States Army Corps of Engineers
(USACE), Washington County, the City of Stillwater, Grant, Dellwood and Stillwater Township.
A corridor study for the entire section of highway 96 was started in 2024 and wrapped up in the
summer of 2026. Throughout the study process, the scope of what the 2028 project would include was
identified. Information on the corridor study can be found here:
https://www.washingtoncountymn.gov/highway96study
The project proposes a pavement preservation style project which will include the replacement of the
existing guardrail, replacement of centerline and driveway culverts and pavement rehabilitation
throughout the corridor. Plans were developed for the replacement of the guardrail throughout the
corridor, but they were never sent out to bid. The project plans can be downloaded here:
https://washingtoncounty.sharefile.com/public/share/web-s247956785b1948c8878818653a606faf
These plans are to be used as a guide, and the selected consultant will be responsible for developing
their own guardrail replacement plans and will include them as part of the final plan set.
1.2. Project Goals and Objectives
The objective of this project is to improve the safety, mobility and pavement condition along the CSAH 96
corridor. In summary, the project goals are as follows:
Page|3
CSAH 96 Improvement Project
Produce municipally approved construction documents that meet all State AID, Washington
County, and local requirements for final design and environmental documentation.
Meet a schedule that ensures project advertisement by January 2028.
Achieve a construction schedule that minimizes public inconvenience, while being sensitive to
reducing overall project costs and environmental impacts.
Review turn lanes at key intersections identified in the highway 96 corridor study and determine
if it’s feasible to implement as part of this project.
Identify and implement stormwater drainage improvements that appropriately
balance the requirements of all agencies with the needs and goals of the
community.
1.3. Project Schedule
Washington County anticipates the following schedule for this project:
Overall Project Schedule
RFP Solicitation
Proposals Due
Consultant Selected
County Board Awards Consultant Contract
Project Kick-off
Data Collection
Environmental Document
60% Plan Submission
3 Week County Review
Open House
ROW Acquisition (If Necessary) (By Washington County)
90% Plan Submission
2 Week County Review
Final Plan Submission
Project Bidding
Pre Construction Open House
Construction
Anticipated Date
May 2026
June 2026
June 2026
August 2026
August 2026
May - August 2026
July – October 2026
April 2027
May 2027
May 2027
April 2027 – January 2028
August 2027
August 2027
October 2027
January 2028
April 2028
Spring/Summer 2028
2. Scope of Work and Deliverables
The following lists outline work tasks and associated items that shall be included as part of the contracted
services.
All reports/documentation must be developed and presented in Microsoft Office and all design files must be
developed and presented in MicroStation/Open Roads Designer (ORD) adhering to Washington County
approved formats unless otherwise noted or requested by the Consultant (the selected firm to perform this
work) with approval of the County.
The role of the selected Consultant team will be to complete all tasks necessary to take the project to a final
set of construction plans. Washington County will act as the lead agency through all aspects of the project.
The County’s role as lead agency does not preclude direct and regular interaction between the Consultant,
the City of Stillwater, Grant, Dellwood and Stillwater Township, the Watershed District, and other agencies.
Page|4
CSAH 96 Improvement Project
External Agency input and review is important; however, the County is to be kept informed of agency dialogue
and will assist the Consultant in determining the need and scope of interaction with a particular agency.
2.1. Project Management
The Consultant will perform all work necessary to effectively coordinate the project completion, maintain
the project schedule and budget, as well as manage the Project Management Team (PMT). The Consultant
will start with an in-person kick-off meeting at the County office. After the kick-off meeting, the Consultant
should host monthly PMT meetings, which will be a mix of virtual and in-person meetings. The proposal
should include a summary of the project management measures required to ensure that the project is
completed on time, within budget, and in accordance with applicable laws, policies, standards, and good
engineering practice. Monthly progress reports shall be submitted with each invoice.
The selected Consultant shall develop and implement a project specific Quality Management Plan, which
shall be available for review upon request during the project.
2.2. Data Collection and Site Visit
The Consultant shall collect existing data and reports relevant to the project area and obtain new
information as needed for all aspects of the project. At least one on-site coordination meeting shall be
arranged by the Consultant. This site visit will include identifying centerline and driveway culverts that
are in need of replacement.
Washington County will provide the following information to the successful Consultant:
Aerial imagery
LIDAR
Topographic Survey (will be provided in July of 2026)
Existing Right of Way information
Construction Plans/Record Drawings
Traffic Counts
Highway 96 Corridor Study
Geotechnical Report from American Engineering Testing
2025 Guardrail Plans
2.3. Public and Agency Engagement
The goal of the Washington County Public Works Department is to achieve excellence in design with every
project we do through comprehensive public involvement. We believe a focused public engagement plan
will be essential to facilitate community acceptance of this project, while maintaining the transportation
objectives and requirements of Washington County, City of Stillwater, Grant, Dellwood and Stillwater
Township.
The Consultant shall develop a Public Involvement Plan to meet the project objective and goals and facilitate
acceptance and approval of the project. The plan should provide an overall approach to involvement, as
well as specific involvement activities, techniques, strategies and how these specific tasks will integrate into
the overall process.
2.3.1. Project Website
Washington County will create a project-specific website, which will be available throughout the
duration of work, as well as throughout construction. The selected Consultant will be responsible
for providing text and graphics to support the website throughout the project.
Page|5
Commodity Codes
  • NAICS 237310Highway, Street, and Bridge Construction
* Disclaimer: Government BidHub provides information on bids, RFPs (Requests for Proposals), and RFQs (Requests for Qualifications) solely for convenience and informational purposes. This site is not an official public notice board. For official details, responses, or inquiries, please contact the relevant government agency directly.

Government Bids

Empower Your Bidding Strategy

Unlock Government BidHub's unparalleled access to high-quality, tailored bid information.

  • Access an extensive database of bids, including comprehensive local and state opportunities.
  • Receive customized alerts for the bids that matter most to your business.
  • Explore detailed specifications to ensure precise and competitive submissions.
  • Gain a competitive edge with up-to-date information and exclusive opportunities.

See Also

I494 Design Build Project 2 V...

I494 Design Build Project 2 Verification Team Brief Description: MnDOT requests responses for

State Government of Minnesota

Bid Due: 7/14/2026

26-21 - Maple Grove Community...

Bid Title: 26-21 - Maple Grove Community Center Phase 2 - BP2 Category:

City of Maple Grove

Bid Due: 7/28/2026