North Charleston, SC - IDF Room Additions (2025-CHS-269)

Project Information

Bid Title
North Charleston, SC - IDF Room Additions (2025-CHS-269)
Issuing Agency
Charleston County International Airport
Location
South Carolina
Published Date
Sep 5, 2025
Closing Date
Oct 16, 2025
Government Level
State & Local
Status
Closed
Original Source
Join to Access Full Details
Project Description
North Charleston, SC - IDF Room Additions (2025-CHS-269)
The Work may be generally described as the interior modification of existing rooms within the commercial terminal building to create three (3) new intermediate distribution frame (IDF) rooms. The project involves providing and installing complete technology systems, cabling and components, as well as additions and modifications to existing mechanical, electrical and fire protection systems and minor modifications to architectural ceilings. Staging and sequencing construction activities are required to be completed in a manner as to not interfere with or interrupt airport operations.
StatusAccepting Bids
Prebid Date 9/23/25 10:00am
Bid Date 10/16/25 2:00pm
Company & Contacts
Charleston Regional Aviation Authority
Carrie Stanley
Location

North Charleston, SC

Any questions and/or comments concerning this Request for Proposal should be directed in writing and delivered via email to Carrie Stanley , Procurement Department at ccaaprocurement@iflychs.com

PREBID CONFERENCE

A MANDATORY Pre-Bid Conference will be held on TUESDAY SEPTEMBER 23, 2025, at 10:00am (local time). Offerors may choose to attend in person at the offices of the Charleston Regional Aviation Authority, 5500 International Blvd, Main Terminal – 3rd floor, North Charleston, SC 29418 or by contacting Carrie Stanley at ccaaprocurement@iflychs.com no later than 24-hours in advance of the scheduled time for teleconference instruction. Firms interested in subcontracting opportunities are invited to attend.

All materials provided by the awarded Contractor must be new, free from defects and must meet CRAA’s specifications. Bidder shall submit the make and model of materials that will be used for the work. After award of contract, no change to materials and products, except when the lack of availability is beyond the Contractor’s control, i.e., due to strike bankruptcy, discontinuance of manufacture, etc. Requests for substitutions shall be made in writing and shall be accompanied by complete description of the substituted material or equipment. Substitution requests must receive written approval from Owner prior to being ordered and installed.

Awarded Contractor shall work with manufacturer of any products installed to ensure that all recommended procedure requirements are adhered to during installation and test to ensure the installation will be valid for manufacturer warranty.

Awarded Contractor shall inspect all products and materials prior to installation. Damaged or nonconforming products and materials shall not be installed.

All Awarded Contractor personnel and subcontractors who will be performing work on this project shall have been trained in the work they will be performing. They shall have been trained on the awarded Contractor’s company policies with respect to safety, quality, and neatness standards.

All fixtures and hardware must be installed per manufacturer’s specifications and in direct coordination with Owner. The Awarded Contractor shall be held financially responsible for any work or re-work required due to improper approval and/or acceptance of that work performed which differs from the construction documents.

CONTRACT TIME

Project is to be substantially complete within 150 consecutive calendar days from the commencement date specified in the written Notice to Proceed and achieve Final Completion within 180 consecutive calendar days.

Commodity Codes
  • NAICS 236220Commercial and Institutional Building Construction
* Disclaimer: Government BidHub provides information on bids, RFPs (Requests for Proposals), and RFQs (Requests for Qualifications) solely for convenience and informational purposes. This site is not an official public notice board. For official details, responses, or inquiries, please contact the relevant government agency directly.

Government Bids

Empower Your Bidding Strategy

Unlock Government BidHub's unparalleled access to high-quality, tailored bid information.

  • Access an extensive database of bids, including comprehensive local and state opportunities.
  • Receive customized alerts for the bids that matter most to your business.
  • Explore detailed specifications to ensure precise and competitive submissions.
  • Gain a competitive edge with up-to-date information and exclusive opportunities.

See Also

Town of Fort Mill Fire Statio...

Project Name: Town of Fort Mill Fire Station #3 Agency/Owner: Town of Fort

State of South Carolina - State Fiscal Accountability Authority(SFAA)

Bid Due: 6/25/2026

Fort Fremont Stairs and Rails...

Project ID: Title: Fort Fremont Stairs and Rails Design/Build Addenda: 0 Release Date:

Beaufort County

Bid Due: 7/02/2026