Idlewood Road Roundabouts at Fellowship Road & Sarr Parkway - ITB 2025-017
Project Information
- Bid Title
- Idlewood Road Roundabouts at Fellowship Road & Sarr Parkway - ITB 2025-017
- Issuing Agency
- City of Tucker
- Location
- Georgia
- Published Date
- Dec 4, 2025
- Closing Date
- Dec 18, 2025
- Government Level
- State & Local
- Status
- Closed
- Ref. #
- ITB 2025-017
- Original Source
- Join to Access Full Details
- Bid Inquiries
- Join to Access Full Details
- Bid Documents
- Join to Access Full Details
- Project Description
-
ITBIdlewood Road Roundabouts at Fellowship Road & Sarr Parkway - ITB 2025-017
Opening Date/Time: November 12, 2025
Closing Date/Time: December 18, 2025
Invitation:The City of Tucker, Georgia requests that interested parties submit bids for the Idlewood Road Roundabouts Project. Bids will be accepted until the date and time listed below and will be awarded to the responsive and responsible bidder whose bid, conforming with all the material terms and conditions of the ITB, is the lowest in price. Addenda and updates to this bid manual will be posted on the Georgia Procurement Registry Website and the City of Tucker website http://tuckerga.gov/bids or may be requested by email procurement@tuckerga.gov.
Bid Activity Schedule- Bid Issued : November 11, 2025
- Pre-Bid Conference In Person Non-Mandatory : November 18, 2025 at 1 p.m.
- Deadline for Questions : November 21, 2025 at 1 p.m.
- Responses to Questions Posted (Addenda) : November 26, 2025
- Bid Deadline : December 18, 2025 at 1 p.m.
- Award at Council Meeting (Tentative) : January 12, 2025 (Tentative)
- Completion from Notice to Proceed : 540 calendar days
- Attachment Preview
-
City of TuckerInvitation to BidITB # 2025-017IDLEWOOD ROAD ROUNDABOUTSFELLOWSHIP ROAD & SARR PARKWAYBID MANUALCity of Tucker1975 Lakeside Parkway, Suite 350Tucker, Georgia 30234Page 1 of 14CITY OF TUCKERITB #2025-017 IDLEWOOD ROAD ROUNDABOUTSINVITATION: The City of Tucker, Georgia requests that interested parties submit bids for the IdlewoodRoad Roundabouts Project. Bids will be accepted until the date and time listed below and will be awardedto the responsive and responsible bidder whose bid, conforming with all the material terms and conditionsof the ITB, is the lowest in price. Addenda and updates to this bid manual will be posted on the GeorgiaProcurement Registry Website and the City of Tucker website http://tuckerga.gov/bids or may be requestedby email procurement@tuckerga.gov.BID ACTIVITY SCHEDULEBid IssuedNovember 11, 2025Pre-Bid Conference In Person Non-Mandatory November 18, 2025, at 1:00pm ESTDeadline for QuestionsNovember 21, 2025, at 1:00pm ESTResponses to Questions Posted (Addenda)November 26, 2025Bid DeadlineDecember 18, 2025, at 1:00pm ESTAward at Council Meeting (Tentative)January 12, 2026 (Tentative)Completion from Notice to Proceed540 calendar daysSCOPE OF WORK: Refer to Exhibit A and provided construction documents prepared by Kimley-Horndated and stamped July, 2025.PRE-BID CONFERENCE: A Non-Mandatory pre-bid conference will be held at 1:00pm EST onTuesday, November 18, 2025, at The City of Tucker City Hall located at 1975 Lakeside Parkway, Suite350, Tucker, Georgia 30084. Representatives of Owner and Design Engineer will be present to discussthe Project. Bidders are strongly encouraged to attend and participate in the conference. The City willtransmit to all prospective bidders such Addenda as necessary in response to questions arising at theconference. Oral statements may not be relied upon and will not be binding or legally effective.QUESTIONS: Submit all questions in writing to procurement@tuckerga.gov with the subject line“Questions: ITB #2025-017” so they are received no later than November 21, 2025 at 1:00 pm EST.ADDENDA: Responses to questions received will be provided by addenda and will be posted on theCity website http://tuckerga.gov/bids. The signed acknowledgement issued with each addendum must besubmitted with the bid. It is the vendor’s responsibility to verify if any addenda were created.SUBMITTAL REQUIREMENTS: Vendor shall submit ITB Response electronically toprocurement@tuckerga.gov so that is received no later than December 18, 2025, at 1:00pm EST with thesubject line “Submittal: ITB #2025-017”. The email must contain the vendor’s contact information.Submittals should be one PDF file and named “<Company Name>.ITB 2025-008.Bid Submittal.pdf”.The submittal email will be opened to confirm receipt of the submittal; however, the attached PDF filewill remain unopened until the public opening.BID OPENING: Bids will be publicly opened at City Hall located at 1975 Lakeside Parkway, Tucker,GA, Suite 350 at 1:00pm EST on Thursday, December 18, 2025.BID SUBMITTALS: A listing of submittals received prior to the bid deadline will be posted on the Citywebsite www.tuckerga.gov/bids following the opening of the bids.Page 2 of 14CITY OF TUCKERITB #2025-017 IDLEWOOD ROAD ROUNDABOUTSPROVIDED REQUIRED FORMS:1. Bid Checklist2. Cost Proposal Form3. Acknowledgement of Addendum issued with each Addendum4. Bid Bond Form5. Contractor Affidavit (E-Verify) Form6. Pre-Qualified / Registered GDOT Work class Checklist Form (Marti to Create)7. Statement of Bidder Qualifications Form8. Related Experience and References Form9. Proposed List of Subcontractors Form10. Statement of Equipment Form11. W-9 Form12. Oath of Non-Collusion13. Contact InformationAll responses must be received electronically by the Bid Deadline. (Addenda will show any scheduleupdates). No bids will be received orally or by phone. Late bids will not be considered. Bids receivedafter the bid deadline will be filed unopened. The City of Tucker reserves the right to reject any and allbids or any part, to waive any formalities to make an award and to re-advertise in the best interest of theCity. The City reserves the right to consider past performance in determining the responsibleness of bidders.The city reserves the right to negotiate pricing and may, in its discretion, award a contract to the lowestresponsible and responsive bidder.Page 3 of 14CITY OF TUCKERITB #2025-017 IDLEWOOD ROAD ROUNDABOUTSExhibit A: Scope of WorkPURPOSE, INTENT, AND PROJECT DESCRIPTIONThe City of Tucker (City), requests that interested parties submit formal electronic bids for theconstruction of the Idlewood Road Roundabouts. The work consists of furnishing and installing allmaterials, labor, tools, equipment, and related services required for a complete project in accordance withthe Contract Documents. The project includes the Idlewood Road at Fellowship Road Roundabout andthe Idlewood Road at Sarr Parkway Roundabout consisting of traffic control, erosion control, clearing andgrading to implement various pedestrian and roadway safety improvements. The intersections will bereconfigured to roundabouts, bike lanes and sidewalks will be realigned, and turn radii will be improvedto increase safety and reduce the chance of collisions. This work is per the Contract Documents for theCity of Tucker's IDLEWOOD ROAD ROUNDABOUTS REDESIGN. The complete scope,specifications, and other relevant information for ITB 2025-017 Idlewood Road Roundabouts is availablefor download on the Georgia Procurement Registry Website and the City of Tucker website(http://tuckerga.gov) or by request via email to procurement@tuckerga.gov.LOCATION: The work under this Contract will be located on Idlewood Road Roundabouts atFellowship Road and Sarr Parkway in Tucker, Georgia. Please see below for approximatevicinity details.Page 4 of 14CITY OF TUCKERITB #2025-017 IDLEWOOD ROAD ROUNDABOUTSGENERAL CONDITIONSThe contractor shall execute the work according to and meet the requirements of the following:• Georgia Department of Transportation (GDOT) Specifications, Standards, and Details.• Contractor and/or subcontractor shall be GDOT Pre-qualified in all related work classesincluding, but not limited to:• Work Class 150 – TRAFFIC CONTROL• Work Class 205 - ROADWAY EXCAVATION• Work Class 209 - SUBGRADE CONSTRUCTION• Work Class:310 - GRADED AGGREGATE CONSTRUCTION• Work Class 400 – HOT MIX ASPHALTIC CONCRETE CONSTRUCTION• Work Class 432 – MILL ASPHALT• Work Class 441 – MISCELLANEOUS CONCRETE• Work Class:550 - STRM DR PIPE, PIPE-ARCH CLVT, SD DR PIPE• Work Class 647 – TRAFFIC SIGNAL INSTALLATION•• Contractor and/or subcontractor shall be GDOT Pre-qualified or Registered in all related workclasses including, but not limited to:• Work Class 163 - MISCELLANEOUS EROSION CONTROL ITEMS• Work Class 167 – WATER QUAILTY MONITORING• Work Class 201 - CLEARING AND GRUBBING RIGHT OF WAY• Work Class 636 – HIGHWAY SIGNS• Work Class 641 – GUARDRAIL• Work Class 653 – THERMOPLASTIC TRAFFIC STRIPE• Work Class 680 – LIGHTING STANDARDS AND LUMINAIRES• The contractor shall have been a licensed general or utility contractor engaged in construction andsuccessful completion of work of similar character and magnitude for at least five years.• The Contract Documents including but not limited to the scope of work, plans, and specifications.• City of Tucker ordinances and regulations.• OSHA standards and guidelines.• MUTCD Guidelines.• Any other applicable codes, laws and regulations including but not limited to Section 45- 10-20through 45-10-28 of the Official Code of Georgia Annotated, Title VI of the Civil Rights Act, Drug-Free Workplace Act, and all applicable requirements of the Americans with Disabilities Act of 1990.• The contractor will be responsible for providing all labor, materials, and equipment necessary toperform the work. This is a unit price bid. Payment will be made based on the actual work completed.• The contractor is responsible for inspecting the jobsite prior to submitting a bid. No change orderswill be issued for differing site conditions.• The successful bidder shall have verifiable experience at construction of roundabout projects inaccordance with these specifications. Bidder shall provide at least three examples and referenceinformation (including company name, project name, contact name, phone number and emailaddress) demonstrating experience of successfully completing projects of similar scope withing thelast ten (10) years. The successful bidder shall also have verifiable experience with traffic controlwhen constructing similar projects within the last ten (10) years. (Reference form provided and maybe duplicated as necessary.)• 5% retainage will be withheld from the total amount due the contractor until Final Acceptance of workPage 5 of 14
- Commodity Codes
-
- NAICS 237310Highway, Street, and Bridge Construction
Empower Your Bidding Strategy
Unlock Government BidHub's unparalleled access to high-quality, tailored bid information.
- Access an extensive database of bids, including comprehensive local and state opportunities.
- Receive customized alerts for the bids that matter most to your business.
- Explore detailed specifications to ensure precise and competitive submissions.
- Gain a competitive edge with up-to-date information and exclusive opportunities.
See Also
MSW Cell No. 6 - Geosynthetic...
Event ID Event Title Government Entity Start Date (ET) End Date (ET) PE-64300-NONST-2026-000000029
State Government of Georgia
Bid Due: 7/15/2026
Description Opening Date/Time Closing Date/Time Red Clay Theatre Mural RFQ June 16, 2026
City of Duluth
Bid Due: 9/01/2026