2026 Sidewalk Replacement Program

Project Information

Bid Title
2026 Sidewalk Replacement Program
Issuing Agency
Garden City city
Location
Michigan
Published Date
Mar 26, 2026
Closing Date
Apr 13, 2026
Government Level
State & Local
Status
Closed
Ref. #
2026-04-13-1000-2
Original Source
Join to Access Full Details
Project Description
Bid Number: 2026-04-13-1000-2
Bid Title: 2026 Sidewalk Replacement Program
Category: Bid Postings
Status: Open
Description:

INVITATION TO BID

GARDEN CITY, WAYNE COUNTY, MICHIGAN

2026 SIDEWALK REPLACEMENT PROGRAM


The one-year project consists of replacing deficient sidewalks throughout Garden City bounded by Ford, Venoy, Warren and Merriman (see attached map).  The anticipated start date, weather

permitting, is May 11, 2026 and substantially completed by November 27, 2026.


SEALED BIDS will be accepted at the Office of the City Clerk, 6000 Middlebelt, Garden

City, MI 48135. Bid must be clearly labeled “2026 SIDEWALK REPLACEMENT PROGRAM”


Two (2) copies of the bid proposals shall be submitted to:

Bryan Smith, City Clerk

City of Garden City

6000 Middlebelt Road

Garden City, MI 48135

Deadline: 10:00 am (est) on Monday, April 13, 2026.

Bids shall be publicly opened and read.


All RFI’s shall be emailed to Nick Yuvan, PE, For security reasons, you must enable JavaScript to view this E-mail address. . (No calls)

The deadline for Request for Information (RFI) is Wednesday, April 8, 2026, 10 a.m. EST.


Contract Documents can be downloaded directly from BidNet.


The OWNER reserves the right to waive any information or to reject any and/or all bids.  Bidders may not withdraw their bid within 60 days after the date of bid opened.


The OWNER and ENGINEER will further assess the bids based on the following criteria.

1.  COST EFFECTIVENESS

2.  SIMILAR PAST PROJECT EXPERIENCE

3.  ABILITY TO RESPOND PROMPTLY WHEN NEEDED


The following items are required for a complete bid submittal:

1.  5% Bid Bond

2.  Completed Itemized Bid Sheet

3.  Completed and Signed Exhibit ‘A’ Proposal

4.  (2) Project References with similar scope

Publication Date/Time:
3/26/2026 5:00 PM
Closing Date/Time:
4/13/2026 10:00 AM
Submittal Information:
Physical Bid Submission: Submit 2 copies of bid proposal in one sealed envelope
Bid Opening Information:
Monday, April 13, 2026 @ 10AM
Contact Person:
Nick Yuvan, Hennessey Engineers

E-Mail: nryuvan@hengineers.com

Plan & Spec Available:
Project specs can be found under Related Documents tab at top of posting.
Special Requirements:
The following items are required for a complete bid submittal:

1. 5% Bid Bond

2. Completed Itemized Bid Sheet

3. Completed and Signed Exhibit ‘A’ Proposal

4. (2) Project References with similar scope

Related Documents:
Attachment Preview
GARDEN CITY
2026 SIDEWALK REPLACEMENT PROGRAM
Advertisement
Instructions to Bidders
General Conditions of Construction Contract
Contract Specifications
Mayor
Mark Jacobs
City Manager
Tim Gibbons
City Clerk
Bryan Smith
Council
Jeff Dold, Mayor Pro-Tem
Kim Dold
Karen Hughes
Dominic King
Stacy Karafotis
Zachary Witt
Director of Public Works
Brad Ohman
47121
1
March 2026
TABLE OF CONTENTS
PART I - BIDDING REQUIREMENTS
PAGE NO.
Invitation to Bid ...................................................................................................................................... 4
Site Map.................................................................................................................................................. 5
Bid Sheet................................................................................................................................................. 6
Instructions to Bidders ...................................................................................................................... 7-10
Special Instructions to Bidders ........................................................................................................ 11-13
Bid Bond .......................................................................................................................................... 14-15
PART II - CONTRACT FORMS
Proposal EXHIBIT A ............................................................................................................................... 16
Agreement ....................................................................................................................................... 17-20
Exhibit B: Performance Bond..........................................................................................................21-22
Exhibit C: Payment Bond ................................................................................................................ 23-24
Exhibit D: Maintenance and Guarantee Bond................................................................................25-26
Contractor's Affidavit for Current Estimate ......................................................................................... 27
Contractor's Affidavit for Final Estimate .............................................................................................. 28
Contractor’s Affidavit for Construction Materials................................................................................ 29
Contractor’s Affidavit for Site Visit and Understanding ....................................................................... 30
PART III - CONDITIONS OF THE CONTRACT
Article 1 — Definitions .................................................................................................................... 31-32
Article 2 — Preliminary Matters........................................................................................................... 33
Article 3 — Contract Documents: Intent and Reuse ........................................................................... 34
Article 4 — Availability of Lands; Physical Conditions; Reference Points ............................................ 35
Article 5 — Bonds and Insurance .................................................................................................... 36-39
Article 6 — Contractor's Responsibility...........................................................................................40-45
Article 7 — Work by Others.................................................................................................................. 46
Article 8 — Owner's Responsibility ...................................................................................................... 47
Article 9 — Engineer's Status During Construction ......................................................................... 47-48
Article 10 — Changes in Work.............................................................................................................. 49
Article 11 — Change of Contract Price ............................................................................................ 50-52
Article 12 — Change of Contract Time ................................................................................................. 52
Article 13 — Warranty and Guarantee: Tests and Inspections; Correction,..................................53-54
Removal or Acceptance of Work
Article 14 — Payments to Contractor and Completion...................................................................55-58
Article 15 — Suspension of Work and Termination ........................................................................ 59-60
Article 16 — Miscellaneous .................................................................................................................. 60
Article 17 — Construction Follow Up ................................................................................................... 61
PART IV - STANDARD NOTES
Garden City Standard Notes ............................................................................................................ 62-66
47121
2
March 2026
PART V – STANDARD SPECIFICATIONS
Traffic Maintenance & Control............................................................................................................. 67
Removing Drive Approaches ................................................................................................................ 68
Removing Sidewalks ............................................................................................................................. 69
Remove Existing Trees & Landscaping ................................................................................................. 69
Aggregate Base (CIP) ............................................................................................................................ 70
Adjusting Structures ............................................................................................................................. 71
Concrete Drive Approach ................................................................................................................ 72-73
Concrete Sidewalk ........................................................................................................................... 74-75
Concrete ADA Ramp with Detectable Warning...............................................................................76-77
Restoration ..................................................................................................................................... 78-81
Sprinkler Repairs................................................................................................................................... 82
Project Cleanup .................................................................................................................................... 82
Utility Coordination .............................................................................................................................. 83
PART V - METHODS AND MEASUREMENT OF PAYMENT
Mobilization.......................................................................................................................................... 84
Traffic Maintenance & Control............................................................................................................. 84
Removing Sidewalks / Ramps............................................................................................................... 85
Removing Existing Trees & Landscaping .............................................................................................. 85
Adjusting Structures ............................................................................................................................. 85
Concrete Drive Approach ................................................................................................................ 85-86
Concrete Sidewalk ................................................................................................................................ 86
7” Concrete ADA Sidewalk Ramp with Detectable Warning...........................................................86-87
Restoration ........................................................................................................................................... 87
Sprinkler Repairs................................................................................................................................... 87
Project Cleanup .................................................................................................................................... 87
PART VIII – DETAILS
CONCRETE SIDEWALK CROSS SECTION ................................................................................................ 88
DETAIL OF CROSS SLOPE TRANSITION.................................................................................................. 89
DRIVE APPROACH JOINT LAYOUT DETAIL............................................................................................. 90
DETAIL OF EXPANSION JOINT ............................................................................................................... 91
DETAIL OF EXPANSION JOINT AT SERVICE SIDEWALKS ........................................................................ 92
47121
3
March 2026
INVITATION TO BID
GARDEN CITY, WAYNE COUNTY, MICHIGAN
2026 SIDEWALK REPLACEMENT PROGRAM
The one-year project consists of replacing deficient sidewalks throughout Garden City bounded by
Ford, Venoy, Warren and Merriman (see attached map). The anticipated start date, weather
permitting, is May 11, 2026 and substantially completed by November 27, 2026.
SEALED BIDS will be accepted at the Office of the City Clerk, 6000 Middlebelt, Garden
City, MI 48135. Bid must be clearly labeled “2026 SIDEWALK REPLACEMENT PROGRAM”
Two (2) copies of the bid proposals shall be submitted to:
Bryan Smith, City Clerk
City of Garden City
6000 Middlebelt Road
Garden City, MI 48135
Deadline: 10:00 am (est) on Monday, April 13, 2026.
Bids shall be publicly opened and read.
All RFI’s shall be emailed to Nick Yuvan, PE, nryuvan@hengineers.com. (No calls)
The deadline for Request for Information (RFI) is Wednesday, April 8, 2026, 10 a.m. EST.
Contract Documents can be downloaded directly from BidNet.
The OWNER reserves the right to waive any information or to reject any and/or all bids. Bidders
may not withdraw their bid within 60 days after the date of bid opened.
The OWNER and ENGINEER will further assess the bids based on the following criteria.
1. COST EFFECTIVENESS
2. SIMILAR PAST PROJECT EXPERIENCE
3. ABILITY TO RESPOND PROMPTLY WHEN NEEDED
The following items are required for a complete bid submittal:
1. 5% Bid Bond
2. Completed Itemized Bid Sheet
3. Completed and Signed Exhibit ‘A’ Proposal
4. (2) Project References with similar scope
City of Garden City
Bryan Smith, City Clerk
47121
4
March 2026
Bridge
Cambridge
Windsor
Dover
Marco
Marcello
Manor Park
Rush
James
Bridge
Cambridge
Windsor
Dover
Chester
Maplewood
Balmoral
Elmwood
Block
Warren
Park
Industrial
Birchlawn
Beechwood
Krauter
Pardo
Ford
Pardo
John Hauk
Donnelly
Bock
Pierce
Hennepin
Brown
Marquette
Barton
Florence
Alvin
Kathryn
Alta
Leona
Kathryn
Alta Venoy
Cir
Brown
Brown
Barton
Sheridan
Florence
Kathryn
Alvin
Kathryn
Leona
Cherry Hill
Leona
Marquette
Rosslyn
Pavillion
Rush
Rush
James
Bridge
Cambridge
Windsor
Dover
Chester
Balmoral
Dawson
Beechwood
Ford
John Hauk
Leona
Balmoral
Block
Dawson
Birchlawn
Beechwood
Krauter
Ford
Pardo
Bock
Donnelly
Hennepin
Brown
Marquette
Barton
Sheridan
Rosslyn
Florence
Alvin
Kathryn
Lytle
Winter
Alvin
Kathryn
Leona
Cherry Hill
Chester
Elmwood
®
2026 SIDEWALKS
GARDEN CITY
STREET MAP
SIDEWALK REPLACEMENT PROGRAM
Commodity Codes
  • NAICS 237310Highway, Street, and Bridge Construction
* Disclaimer: Government BidHub provides information on bids, RFPs (Requests for Proposals), and RFQs (Requests for Qualifications) solely for convenience and informational purposes. This site is not an official public notice board. For official details, responses, or inquiries, please contact the relevant government agency directly.

Government Bids

Empower Your Bidding Strategy

Unlock Government BidHub's unparalleled access to high-quality, tailored bid information.

  • Access an extensive database of bids, including comprehensive local and state opportunities.
  • Receive customized alerts for the bids that matter most to your business.
  • Explore detailed specifications to ensure precise and competitive submissions.
  • Gain a competitive edge with up-to-date information and exclusive opportunities.

See Also

Site Improvements at St. Aubi...

Project: Site Improvements at St. Aubin, Belle Isle, and Baby Creek CSO Facilities

Great Lakes Water Authority

Bid Due: 7/07/2026

Summer Renovations Project

Description: Summer Renovations Project Department: Davison Community Schools Buyer: Rod Hoover Solicitation Number:

State of Michigan

Bid Due: 7/14/2026