Description Opening Date/Time Closing Date/Time


Woodhaven Driveway Replacement and Asphalt Paving


Addendum 1 - Questions



May 13, 2026
:


June 25, 2026
1:45
PM

Attachment Preview
ADDENDUM NO. 1
TO
CONTRACT DOCUMENTS
WOODEHAVEN DRIVEWAY REPLACEMENT AND ASPHALT PAVING
DULUTH, GEORGIA
BIDS DUE JUNE 25, 2026
No. QUESTION
RESPONSE
1 The curb is poured monolithic on Folkstone Dr, Remove driveway and curb and replace both.
is it the city’s preference to remove driveway
and curb or pour driveway and saw cut, leaving
original curb?
2 There is no line item for asphalt patching, can Asphalt patching will be added.
one be added in case it is needed?
3 For the milling, is the 1.5” off of the existing or 1.5” off the existing.
below the gutter line? Some of the streets have
been overlayed and asphalt is above the curb.
4 Home owners have poured concrete in the
We expect careful effort be made to not disturb
gutter line in front of the driveways. When we the concrete in the gutter in front of driveways,
are milling and paving if those come loose or
but they are not the contractor’s responsibility
break, are we required to pour those back?
to fix because Duluth does not allow these.
5 Will payment be based on field measurements Payment will be based on field measurements.
or the exact quantities on the line items?
6 Asphalt Patching
Asphalt patching will be added.
The plans reference patching as part of the mill
and inlay detail; however, the bid form does
not appear to include a separate patching item.
Should asphalt patching be considered
incidental to the milling/asphalt items, or will it
be paid separately if required?
7 Unsuitable Soils
Yes, it should include the items you mentioned.
For the unsuitable soils item, please confirm
57 Stone.
whether the unit price should include
excavation, haul-off, disposal, replacement
material, placement, and compaction. Also,
please clarify what replacement material should
be assumed.
8 Resident Parking / Driveway Access
The City will coordinate with residents on
Will the City or HOA provide temporary parking temporary parking during construction. There
areas for residents during concrete removal,
is on-street parking to be utilized.
replacement, and curing, or will the contractor
be responsible for coordinating and maintaining
resident parking/access?
Addendum Prepared By
KECK & WOOD, INC.
June 12, 2026
Commodity Codes
  • NAICS 237310Highway, Street, and Bridge Construction
  • NAICS 238990All Other Specialty Trade Contractors
* Disclaimer: Government BidHub provides information on bids, RFPs (Requests for Proposals), and RFQs (Requests for Qualifications) solely for convenience and informational purposes. This site is not an official public notice board. For official details, responses, or inquiries, please contact the relevant government agency directly.

Government Bids

Empower Your Bidding Strategy

Unlock Government BidHub's unparalleled access to high-quality, tailored bid information.

  • Access an extensive database of bids, including comprehensive local and state opportunities.
  • Receive customized alerts for the bids that matter most to your business.
  • Explore detailed specifications to ensure precise and competitive submissions.
  • Gain a competitive edge with up-to-date information and exclusive opportunities.

See Also

26-272 Deans Bridge Road MSW ...

Event ID Event Title Government Entity Start Date (ET) End Date (ET) PE-72155-NONST-2026-000000194

State Government of Georgia

Bid Due: 8/06/2026

160-172 Dalrymple Road Stormw...

Project: 160-172 Dalrymple Road Stormwater Improvement Ref. #: 26-053 Type: ITB Status: Open

City of Sandy Springs

Bid Due: 7/07/2026