2026-0198-PW Construction Services for the Arroyo Hondo SR-14 Interceptor Addendum No. 6

Project Information

Bid Title
2026-0198-PW Construction Services for the Arroyo Hondo SR-14 Interceptor Addendum No. 6
Issuing Agency
Santa Fe County
Location
New Mexico
Published Date
Apr 1, 2026
Closing Date
Apr 10, 2026
Government Level
State & Local
Status
Closed
Original Source
Join to Access Full Details
Project Description

ifb

2026-0198-PW Construction Services for the Arroyo Hondo SR-14 Interceptor

2026 0198 PW IFB Construction Services for the Arroyo Hondo SR14 Sewer Interceptor.pdf

SFC SR-14 Sewer Interceptor Supplemental Technical Specifications.pdf

SFC SR-14 Sewer Interceptor Drawings.pdf

SFC SR-14 SR-14 Sewer Interceptor Geotech - Final Report.pdf

Addendum No. 1 IFB 2026-0198-PW Const Serv of the Arroyo Hondo SR-14 Sewer Interceptor.pdf

Addendum No. 2 IFB 2026-0198-PW Const Serv of the Arroyo Hondo SR-14 Sewer Interceptor.pdf

Addendum No. 3 IFB 2026-0198-PW Const Serv of the Arroyo Hondo SR-14 Sewer Interceptor.pdf

Addendum No. 4 IFB 2026-0198-PW Const Serv of the Arroyo Hondo SR-14 Sewer Interceptor.pdf

Addendum No. 5 IFB 2026-0198-PW Const Serv of the Arroyo Hondo SR-14 Sewer Interceptor.pdf

Addendum No. 6 IFB 2026-0198-PW Const Serv of the Arroyo Hondo SR-14 Sewer Interceptor.pdf

Attachment Preview
Justin S. Greene
Commissioner, District 1
Lisa Cacari Stone
Commissioner, District 2
Camilla Bustamante
Commissioner, District 3
Adam Fulton Johnson
Commissioner, District 4
Hank Hughes
Commissioner, District 5
Gregory S. Shaffer
County Manager
April 1, 2026
SANTA FE COUNTY
IFB No. 2026-0198-PW/TJ
CONSTRUCTION SERVICES FOR THE
ARROYO HONDO SR-14 SEWER INTERCEPTOR
ADDENDUM NO. 6
Dear Proponents,
This addendum is issued to reflect the following immediately. It shall be the responsibility of
interested Offerors to adhere to any changes or revisions to the IFB as identified in this Addendum
No. 6. This documentation shall become permanent and made part of the departmental files.
BID OPENING EXTENDED TO
FRIDAY, APRIL 10, 2026 @ 2:00 PM
Attachment A: Revised Bid Sheet (based on the lowest, responsive base bid)
Question No. 1:
Answer No. 1:
Question No. 2.:
Answer No. 2:
Having said that, we are a bit confused as to why there are two mobilizations
if this is the same base bid.
Bid Item #40 mobilization/demobilization under the Colibri Sewer Re-route
shall be struck and removed entirely and will be considered “NOT USED”.
Bid Item No. #1 for Mobilization and demobilization shall be for the entirety
of the project, including the SR-14 Sewer Interceptor and Colibri Sewer Re-
route.
We are in receipt of Addendum No. 5, and the note requiring interior coatings
was removed from the Bid Items #9, 10, and 11. However, it is still calling for
interior coatings on the Colibri Reroute manholes, Items #52 and 53.
The Bid Item descriptions of Bid Items #52 and 53 shall be revised to strike
and removed “interior epoxy coating” from the bid item descriptions. There
will be no interior coatings required for manholes on this project.
102 Grant Avenue · P.O. Box 276 · Santa Fe, New Mexico 87504-0276 · 505-986-6200 · FAX:
505-995-2740 www.santafecountynm.gov
Please add this Addendum No. 6 to the original proposal documents and refer to proposal documents,
hereto as such. This and all subsequent addenda will become part of any resulting contract documents
and have effects as if original issued. All other unaffected sections will have their original
interpretation and remain in full force and effect. Responders are reminded that any questions or need
for clarification must be addressed to Tammy Jim, Procurement Specialist Senior at
tjim@santafecountynm.gov.
102 Grant Avenue · P.O. Box 276 · Santa Fe, New Mexico 87504-0276 · 505-986-6200 · FAX:
505-995-2740 www.santafecountynm.gov
Item No.
ATTACHMENT A
Santa Fe County
SR-14 Gravity Sewer Interceptor
Description
Unit
SR-14 Sewer Interceptor (C-1 to C-31)
1
Mobilization (75%) and Demobilization (25%), not to exceed 7%
of the Base Bid
2
Material Testing Allowance
Furnish and install 10-inch PVC SDR-26 gravity sewer interceptor
3
(including all materials, labor, fittings, tracer wire, bedding,
warning tape), CIP
Furnish and install 8-inch PVC SDR-26 gravity sewer interceptor
4
(including all materials, labor, fittings, tracer wire, bedding,
warning
tape), CIP
LS
Allow
LF
LF
Furnish and install 18-inch Diameter Jack and Bore across road
5
crossing, with 18" Steel Casing, including all materials, labor,
fittings, carrier pipe, spacers, end seals, bore pit excavation,
LF
bedding, backfill, and site restoration, CIP.
Trenching, Backfilling, and Compaction for new Gravity Sewer
6
Pipe, up to 8-ft in depth, including equipment and labor. Pipe not
LF
included. CIP
Trenching, Backfilling, and Compaction for new Gravity Sewer
7
Pipe,
from 8-ft to 12-ft in depth, including equipment and labor. Pipe
LF
not included. CIP
Trenching, Backfilling, and Compaction for new Gravity Sewer
8
Pipe, from 12-ft to 16-ft in depth, including equipment and labor.
Pipe not
LF
included. CIP
Furnish and Install 4-ft Diameter Precast Type C Concrete
Manhole, up to 8-ft in depth to invert, including cover, collar, lid,
9
grade adjustment rings, new sewer line connections and all
EA
materials, labor, excavation, backfill, compaction, testing, and site
restoration, CIP.
Furnish and Install 4-ft Diameter Precast Type C Concrete
Manhole, from 8-ft to 12-ft in depth to invert, including cover,
10 collar, lid, grade adjustment rings, new sewer line connections and EA
all materials, labor, excavation, backfill, compaction, testing, and
site restoration, CIP.
Revised: 04/01/2026
Est.
Quantity
Unit Price
Total Price
1
1
17200
$ 200,000.00 $ 200,000.00
430
120
6505
10465
660
17
32
Furnish and Install 4-ft Diameter Precast Type C Concrete
Manhole, from 12-ft to 16-ft in depth to invert, including cover,
11 collar, lid, grade adjustment rings, new sewer line connections and EA
6
all materials, labor, excavation, backfill, compaction, testing, and
site restoration, CIP.
Furnish and Install 8-inch PVC SDR-26 stubout for future
12
connection, including all material, caps, fittings, labor, trenching,
tracer wire, bedding, warning tape, backfilling, compaction, and
EA
site restoration, CIP.
13
Connect New Gravity Sewer Line to Existing Manhole, including
all materials, labor, piping, fittings, trenching, and backfill, CIP.
EA
14
Connect Existing Gravity Sewer Line to New Manhole, including
all materials, labor, piping, fittings, trenching, and backfill, CIP
EA
15
New Sewer Line Testing, including CCTV Inspection, Air
Testing, and Mandrel Test, Complete.
LF
16
Temporary bypass pumping for connection to existing sewer
manhole, CIP
LS
Remove and replace existing asphalt to match existing grade,
including 12-inch subgrade preparation, 6-inch basecourse, 6-inch
17 Asphalt Pavement HMA PIV, all materials, labor, saw-cutting and SY
disposal of
material, CIP.
18 Traffic Control
LS
19
Construction Staking, including pipe alignments, appurtenances,
and surveyed as-builts, CIP.
LS
20 Preparation and implementation of SWPPP
LS
SR-14 Access and Maintenance Road (RD-3 to RD-22)
21 Site Clearing and Grubbing, complete
AC
Fill, construction, incl. excavation, placement , compaction of
22 unclassified material, over 2 ft. deep, and removal & disposal of
CY
excess material per NMDOT 203000, CIP.
23 Subgrade Preparation, CIP.
SY
24 Furnish and install Base Course 6", CIP.
SY
25
Furnish and install Drivepad, 6" thick, Portland Cement Concrete,
incl. subgrade compaction, CIP.
SY
26
Furnish and install Curb & Gutter, Standard, Portland Cement
Concrete, incl. subgrade preparation, CIP.
LF
27
Remove, dispose & replace existing Curb & Gutter, PC Concrete,
CIP.
LF
28 Remove and dispose of Existing Sidewalk, 4" PC Concrete, CIP.
SY
29 Remove & replace Existing Fence, match in-kind, CIP.
LF
30
Furnish and install Pipe Gate, 12' wide, incl. all attachments,
hardware & anchor posts, CIP.
EA
31
Furnish and install Pipe Gate, 20' wide, incl. all attachments,
hardware & anchor posts, CIP.
EA
32 Furnish and install Reinf. Concrete for Minor Structures, CIP.
CY
33
Furnish and install 18" Culvert Pipe per NMDOT 570018, incl.
trench & compacted backfill to 6' depth, CIP.
LF
34
Furnish and install 18" Culvert Pipe End Section per NMDOT
570019, CIP.
EA
3
1
2
17750
1
865
1
1
1
11
3400
15344
15344
15
24
22
6
190
2
1
5
110
12
35
Furnish and install 24" Culvert Pipe per NMDOT 570024, incl.
trench & compacted backfill to 6' depth, CIP.
36
Furnish and install 24" Culvert Pipe End Section per NMDOT
570025, CIP.
37
Furnish and install 30" Culvert Pipe per NMDOT 570030, incl.
trench & compacted backfill to 6' depth, CIP.
38
Furnish and install 30" Culvert Pipe End Section per NMDOT
570031, CIP.
39 Furnish and install Riprap Class A, per NMDOT 602000, CIP.
40 Furnish and install Seeding, Class "A", native, CIP.
Colibri Sewer Re-Route
41 Material Testing Allowance
42 Utility Relocation Allowance
43 Traffic Control
44 Temporary Bypass Bumping
Furnish and install 12-inch PVC SDR-35 gravity sewer interceptor
45 (including all materials, labor, fittings, tracer wire, bedding,
warning tape), CIP.
Furnish and install 8-inch PVC SDR-35 gravity sewer interceptor
46 (including all materials, labor, fittings, tracer wire, bedding,
warning tape), CIP.
Trenching, Backfilling, and Compaction for new Gravity Sewer
47 Pipe, up to 8-ft in depth, including equipment and labor. Pipe not
included. CIP.
Trenching, Backfilling, and Compaction for new Gravity Sewer
48 Pipe, from 8-ft to 12-ft in depth, including equipment and labor.
Pipe not included. CIP.
Trenching, Backfilling, and Compaction for new Gravity Sewer
49 Pipe, from 12-ft to 16-ft in depth, including equipment and labor.
Pipe not included. CIP.
Trenching, Backfilling, and Compaction for new Gravity Sewer
50 Pipe, from 16-ft to 20-ft in depth, including equipment and labor.
Pipe not included. CIP.
51
Concrete encasement of 12" SDR 35 PVC sewer line, complete in
place, including reinforcement.
Furnish and Install 4-ft Diameter Precast Type C Concrete
Manhole, from 8-ft to 12-ft in depth to invert, including cover,
52 collar, lid, grade adjustment rings, new sewer line connections and
all materials, labor, excavation, backfill, compaction, testing, and
site restoration, CIP.
LF
EA
LF
EA
CY
AC
Allow
Allow
LS
LS
LF
LF
LF
LF
LF
LF
LF
EA
Furnish and Install 4-ft Diameter Precast Type C Concrete
Manhole, from 12-ft to 16-ft in depth to invert, including cover,
53 collar, lid, grade adjustment rings, new sewer line connections and EA
all materials, labor, excavation, backfill, compaction, testing, and
site restoration, CIP.
54 Remove & Dispose of Existing Manhole, CIP
EA
50
4
18
1
30
8
1
1
1
1
1736
$ 15,000.00
$ 10,000.00
$ 15,000.00
$ 10,000.00
40
154
367
1241
19
170
1
11
1
Commodity Codes
  • NAICS 236220Commercial and Institutional Building Construction
  • NAICS 237990Other Heavy and Civil Engineering Construction
* Disclaimer: Government BidHub provides information on bids, RFPs (Requests for Proposals), and RFQs (Requests for Qualifications) solely for convenience and informational purposes. This site is not an official public notice board. For official details, responses, or inquiries, please contact the relevant government agency directly.

Government Bids

Empower Your Bidding Strategy

Unlock Government BidHub's unparalleled access to high-quality, tailored bid information.

  • Access an extensive database of bids, including comprehensive local and state opportunities.
  • Receive customized alerts for the bids that matter most to your business.
  • Explore detailed specifications to ensure precise and competitive submissions.
  • Gain a competitive edge with up-to-date information and exclusive opportunities.

See Also

Residential Roof Repair Coati...

Follow Residential Roof Repair Coating Services Active Contract Opportunity Notice ID 19MX5326Q0041 Related

STATE, DEPARTMENT OF

Install Sidewalk Dyer, Aberde...

Follow Install Sidewalk Dyer, Aberdeen to MLK Active Contract Opportunity Notice ID W911SG26BA003

DEPT OF DEFENSE

Bid Due: 7/16/2026