RFP: Fuel Farm Addendum #1
Project Information
- Bid Title
- RFP: Fuel Farm Addendum #1
- Issuing Agency
- Birmingham Airport Authority
- Location
- Alabama
- Published Date
- Nov 20, 2025
- Closing Date
- Dec 18, 2025
- Government Level
- State & Local
- Status
- Closed
- Original Source
- Join to Access Full Details
- Bid Inquiries
- Join to Access Full Details
- Bid Documents
- Join to Access Full Details
- Project Description
-
RFP: Fuel Farm Addendum #1 (11/20/2025)
- Attachment Preview
-
REQUEST FOR PROPOSAL (RFP)ADDENDUM NUMBER ONE (1)DATE: November 20, 2025PROJECT:From:To:Design-Build of Three (3) 25,000 Gallon Jet A Tanks at Fuel Farm B and Two(2) 25,000 Gallon Jet A Tanks at Fuel Farm CBirmingham-Shuttleworth International AirportBirmingham, AlabamaBirmingham Airport Authority (BAA)5900 Messer Airport HighwayBirmingham, Alabama 35212All ParticipantsGeneral:This addendum will form a part of the RFP and modifies the original Request for Proposal (RFP)document. The following changes take precedence over items in the RFP. Any portion of theRFP not changed by this Addendum remains in effect. Recipients of the Addendum are advisedto provide this Addendum to anyone to whom they further distribute without the BAA’sknowledge.Participants in this RFP are required to acknowledge receipt of this Addendum in their proposal.Failure to do so may subject Proposer for disqualification.ADDITIONAL INFORMATION/CLARIFICATIONS/DESCRIBED BELOW:1. Question: Please provide the permitting authority having jurisdiction over the airport for siteand/or building permits.Answer: Applicable City of Birmingham and Jefferson County permits will need to beacquired for this project. The Airport Authority does not issue or approve permits.2. Question: Can more information be provided for the extent of the environment analysis andpermitting for this project.Answer: The BAA anticipates a CATEX for this project. If more environmental assessmentis needed, the BAA will amend the scope of work with the successful respondent to includethe added effort. Respondents should include at least a CATEX in their proposals.3. Question: Are there any DBE requirements or goals for this project?Answer: No4. Question: Can more information be provided on the fire detection safety devices that arerequired in Section D or should devices only required by code be provided?Answer: Code required devices and devices required by the local AHJ via amendments to thecoder are to be provided.5. Question: Please confirm that an official design submittal is not required for this project forreview prior to construction and only the shop drawings and product data submittals arerequired per Section E prior to construction.Answer: Prior to construction, the BAA will require at least the following:• Stamped construction ready plan set• BAA and FAA approved Safety and Phasing Plan• Specification Manual• All applicable local permits in hand• Submittal reviews• COI – Airside requirements• NTP6. Question: Within the Introduction it is stated that, “the anticipated date of completion of theproject… is November 2026”, however, the Tentative RFP Timeline states a contract date ofFebruary 2026. Based on this schedule, there would only be 7-months to design, permit andconstruct both facility’s improvements (it was stated that the facility work requires phasing,one farm after the other), which is not feasible given the current proposed improvements andequipment lead time (some electrical gear lead time is upwards of 40-weeks currently). Canthe airport confirm their desired schedule?Answer: The BAA’s intent is that the project schedule progress at an expeditious pace inorder to complete the project in a reasonable time frame. It is our preference to complete theproject efficiently and without delay. However, we also understand lead time and operationalconstraints are realistic limitations that must be accounted for when developing projectschedules. The BAA is open to a new and reasonable schedule and will work with theselected firm to find an acceptable compromise.7. Question: Will the Design-Build Agreement include liquidated damages?Answer: Yes, liquidated damages will be $1,000 per day8. Question: Is there a specimen Design-Build Agreement available for review before thesubmission of bids?Answer: AIA Document A141-2024 standard form of Agreement between owner and designbuilder will be used. We do not have the completed Agreement to share at this time.9. Question: SOW Section D. Technical Requirements - Bullet 12 states to provide firedetection safety devices for all dispensers and the station equipment, including any upgradesto ventilation, electrical, heating and fire control panels… What type of fire detectionequipment is required? The reference to ventilation, electrical, and heating appears to havebeen copied from a building project and would not apply to a fuel facility.Answer: Code required detection devices and devices required by the local AHJ viaamendments to the coder are to be provided. Ventilation is not anticipated to be required onthis project but is the Design-Builders responsibility to verify with the code to ensure that it isnot required.10. Question: SOW Section D. Technical Requirements - Bullet 14 states for all new tanks to sitwithin tertiary concrete containment basin suitable for a one tank failure. Per NFPA andEnvironmental regulations, double-walled tanks do not need tertiary containment. Do youstill want us to price a tertiary containment system?Answer: Yes, a tertiary containment is required by the Airport for this project and should bepriced into the proposal.11. Question: SOW Section E Other Scope Requirements - Paragraph 5 states, the Design-Builder shall be responsible for an environmental analysis of the new fuel systems as well asall associated environmental permitting for this Project. What exactly is the intent of thisparagraph? Will a CATEX be granted by the FAA, or will the airport need to go through theNEPA process? Is there known contamination within the fuel farms? Have anyenvironmental testing or studies been conducted at the fuel farms and if so, is theredocumentation that can be shared about the results of these tests or studies?Answer: The BAA anticipates a CATEX for this project. If more environmental assessmentis needed, the BAA will amend the scope of work with the successful respondent to includethe added effort. Respondents should include at least a CATEX in their proposals.12. Question: SOW Section I Final Acceptance of Construction Work bullet point 5 requires“operation and maintenance manuals”. Is the intent of this to have the Design-Builderprovider manufacturer O&M manuals for supplied equipment, as is normal and typical, or isthe airport desiring a facility specific O&M manual developed in accordance with the ATAFFO-2004 Airport Fuel Facility Operations and Maintenance Guidance Manual (or otherindustry standard)?Answer: The desire is for a facility specific O&M manual in accordance with ATA FFO-2004but also ensure all O&M manual for specific equipment is also provided.13. Question: SOW Section I Final Acceptance of Construction Work - the last paragraph liststhat maintenance manuals, parts lists and procedures for all systems, equipment andcomponents shall be updated by the Contractor for a period of 10 years. Ongoing updates ofequipment manuals and components is not typically required for a Design-Buildcontractor. Keeping up with ongoing updates for 10 years for all equipment and componentswill add significant up-front costs to the project that don't provide any immediate rate ofreturn on the expenditure. Most equipment installed is warranted for 1 year after SubstantialCompletion. Doing ongoing equipment manual updates would normally be done as part of anongoing Engineering Support Service (ESS) contract after the fuel facility isconstructed. Can the airport confirm if this scope item is required?Answer: No. Ongoing updates to equipment manuals and components are not required.However, the BAA will require that maintenance manuals and warranty documents be turnedover to BAA staff prior to Final Completion.14. Question: SOW Section E Other Scope Requirements - Paragraph 6 discusses the electricalpower systems serving both fuel farms. As the scope relates to electrical coordination withthe Utility, we can include this, but can the airport please confirm that the existingservice/size/capacity at each farm can support the added improvements? As many elementsare being added, we need to differentiate what costs to carry in the design/build costs versuswhat will be carried by the Authority/Utility. If capacity needs increase, will an increase inService Capacity be borne by the Authority/Utility?Answer: Service capacity verification is part of the scope of this project. Design-Buildcontractor shall assume that sufficient capacity exists for the scope of the project. If capacityneeds increase, then the scope will amend via change order for that portion of the project.15. Question: Please clarify the method of proposal submittal and the number of physical copies(if any) to be supplied. At the pre-submittal meeting, it was stated that three physical copieswere required. In Section III.B. of the RFP, it states that five physical copies and oneelectronic copy (on a flash drive) are required to be submitted.Answer: Five copies are required along with an electronic copy on a flash drive.16. Question: What are the allowable on-site workdays and times? (Confirm M-F 5a-5p)Answer: Work is allowed any day of the week during daylight hours.17. Question: Please confirm that a site superintendent will be required onsite full-timethroughout the duration of the project.Answer: Yes, a superintendent must be on site any time active work is being done on site.18. Question: Can the HSSE representative be the same individual as the site superintendent?Answer: Yes, the HSSE can be the same individual as the site superintendent.19. Question: Please confirm that the facility currently has a maximum fuel storage of 0.8 days.Answer: Max usable storage capacity is 2.5 days of average uplift between all fuel farms atthe airport. Fuel Farm B and C are responsible for most of the uplift at the airport and have a1.8 day usable capacity at max fill assuming no transfer from other farms.20. Question: Please confirm that the facility will make arrangements for temporary bulk storageupon adequate notification from the Design-Build contractor.Answer: Yes, the airport will make arrangements for temporary bulk storage.21. Question: What is the maximum allowable downtime for each fuel storage site and, ifapplicable, for both sites simultaneously?Answer: Both sites shall not be down simultaneously, this is reason for the phased approach.Max downtime shall be kept an absolute minimum and shall be limited to less than 1 week.22. Question: What is the minimum required notification for planned system downtime for eachscenario listed above?Answer: 60 days23. Question: How many Access Badge Signatory Authorities may be assigned to a singlecontractor?Answer: Maximum of three (3), dependent upon the number of badge holders.24. Question: Does each subcontractor need to have its own Access Badge SignatoryAuthority(ies), or can a higher-tier contractor act as the Signatory Authority for itssubcontractor(s)?Answer: A higher-tier contractor may act as a Signatory Authority for its subcontractors.25. Question: How long on average are the processes to approve Signatory Authorities and/oraccess badge applicants? (Is 30 days still the expected time to wait for badge approval?)Answer: Up to 30 days.26. Question: How long does the on-site badge applicant training take?Answer: 2-3 hours27. Question: How long are the Access ID Badges valid for? (Is it anticipated that badgeapplicants will need to renew their badges at any point throughout the project duration?)Answer: One year28. Question: Will a badged employee be allowed to escort visitors or other unbadgedemployees?Answer: Yes. Badged personnel with escorting privileges will be able to escort visitors orother unbadged employees.29. Question: Is there a separate procedure for authorizing vehicle access to the project area?Answer: Vehicles accessing the project area fall under the responsibility of the Design-Buildcontractor and are subject to the requirements defined in the Airport’s Contractor Safety andSecurity Program.30. Question: What requirements exist for contractor vehicles that enter the restricted areas ofthe airport?Answer: See question 29.31. Question: Do subcontractors need to carry the same insurance coverage as the primarycontractor(s)?Answer: The primary contractor is the responsible party for meeting the insurancerequirements for the project.32. Question: What is the current power capacity being supplied to the existing system?Answer: Service capacity verification is part of the scope of this project. Design-Buildcontractor shall assume that sufficient capacity exists for the scope of the project. If capacityneeds increase, then the scope will amended via change order for that portion of the project.33. Question: What is the current power voltage being supplied to the existing system (e.g., 240-1P, 208-3P, 240-3P)? If the supplied voltage is three phase, is there a dedicated neutral on thepower supply?Answer: Believed to be 240-3P. Uncertain of the neutral on power supply.
- Commodity Codes
-
- NAICS 324110Petroleum Refineries
* Disclaimer: Government BidHub provides information on bids, RFPs (Requests for Proposals), and RFQs (Requests for Qualifications) solely for convenience and informational purposes. This site is not an official public notice board. For official details, responses, or inquiries, please contact the relevant government agency directly.
Empower Your Bidding Strategy
Unlock Government BidHub's unparalleled access to high-quality, tailored bid information.
- Access an extensive database of bids, including comprehensive local and state opportunities.
- Receive customized alerts for the bids that matter most to your business.
- Explore detailed specifications to ensure precise and competitive submissions.
- Gain a competitive edge with up-to-date information and exclusive opportunities.
See Also
Troubleshoot/Repairs to Rollu...
Sourcing Project Number: SRC0000034386 Solicitation Label: Troubleshoot/Repairs to Rollup Door at Gadsden MAS/Ira
State Government of Alabama
Bid Due: 7/15/2026
Housing Implementation & Inve...
Project ID: Title: Housing Implementation & Investment Proposal Addenda: 0 Release Date: 6/3/2026
City of Montgomery
Bid Due: 7/15/2026