City Hall Improvements ? Building 4 Front Counter Remodel CIP 2024-30 (Re-Bid)

Project Information

Bid Title
City Hall Improvements ? Building 4 Front Counter Remodel CIP 2024-30 (Re-Bid)
Issuing Agency
City of Santee
Location
California
Published Date
Jun 22, 2026
Closing Date
Jul 2, 2026
Government Level
State & Local
Status
Closed
Ref. #
25/26-20096
Original Source
Join to Access Full Details
Project Description
City Hall Improvements – Building 4 Front Counter Remodel CIP 2024-30 (Re-Bid)
RFP Number:
25/26-20096
Start Date:
2026-06-01 10:00 AM
Close Date:
2026-07-02 5:00 PM

Time for Completion: 100 working days

Project Budget: $240,000.00

Questions:

Any questions relating to this RFP should be directed to Antonio Sandoval at (619) 258-4100 x 179, or via email at asandoval@cityofsanteeca.gov

Documents:
Attachment Preview
June 22, 2026
To Prospective Proposers:
City Hall Improvements Building 4 Front Counter Remodel
RFP #25/26 - 20096
ADDENDUM NO. 1
This Addendum No. 1 (10 pages in total) forms an essential part of the contract documents by revising
the following:
1A CHANGES / ADDITIONS / DELETIONS TO THE PROPOSAL DOCUMENTS
1A-1 Add Attachment ‘E’ – City Hall Landscape Irrigation As-Built Drawings, 6 sheets total.
1B RESPONSES TO QUESTIONS RECEIVED DURING THE PRE-PROPOSAL MEETING
The following items are responses to questions received during the pre-proposal meeting for the
RFP:
1B-1 Question: The Notice of Rebid identifies a project budget of $240,000. Please confirm whether
this amount is for budgetary/planning purposes only, or whether proposals exceeding $240,000
will be deemed non-responsive or otherwise ineligible for award.
Response: The City listed an estimated budget of $240,000 for this Project to complete all design
and construction services required in this RFP. Proposals with a proposed cost exceeding the
City’s estimated budget will not be deemed non-responsive or be ineligible for award soley based
on price.
1B-2
Question: The project is identified as design-build. Please clarify whether the drawings issued
with the RFP are approved permit/construction documents, or whether the selected contractor is
responsible for preparing, stamping, submitting, revising, and/or obtaining approval of additional
design or permit documents, including any Title 24, electrical, low-voltage, fire alarm, accessibility,
or deferred-submittal documentation.
Response: The provided Building Four Front Counter Improvements Plan”, Exhibit ‘A’, is
approved by the City’s Building Department for the Building permit required for this project. The
Selected Firm shall be responsible for preparing, stamping, submitting, revising as required to
obtain approval of the additional design submittals listed in “Section 2.2.2 Design Submittals” for
the Building permit. The Selected Firm shall reference Exhibit ‘A’, for preparation of these
additional design submittals.
1B-3
Question: Please confirm the complete list of documents, drawings, specifications, exhibits,
standards, prior addenda, and attachments that proposers must base their proposal on. Because
this a rebid, please also identify any scope, drawing, specification, budget, schedule, or proposal-
form changes from the prior solicitation.
Response: No prior addendums have been issued for the current solicitation of this RFP.
Prospective proposers shall base their proposal on the information provided in the current RFP
#25/26 – 20096 listed on the City’s website. The only changes between the current and prior
solicitation are:
1) Estimated budget was increased from $230,000 to $240,000; and
2) “Section 2.1.9 Suspended T-bar Ceiling System”, requirements that existing spiral ducting and
new duct extensions in unconditioned spaces will need to be wrapped with minimum R-8 duct
wrap insulation.
All modifications to the RFP from addendums in the prior solicitation were incorporated into this
current solicitation.
1B-4
Question: The RFP scope references casework and furnishing. Please provide complete
specifications and limits of work for the front counter/casework and any furnishings, including
materials, finishes, hardware, countertop requirements, ADA counter requirements,
transaction/pass-through requirements, security glazing if any, loose furniture if any, owner-
furnished items, and any required installation of owner-furnished equipment.
Response: Refer to “Section 2.1.8 Casework” and “Section 2.1.10 Site Fixtures, Furnishings, and
Equipment” for specifications and quantities of casework and furnishings. Refer to Exhibit ‘A’ for
locations of where casework and furnishings are to be placed. Nothing in this contract will be
owner-furnished or require installation of owner-furnished equipment.
1B-5
Question: Please confirm the full electrical, data, and low-voltage scope required at the front
counter remodel area, including receptacles, data drops, floor boxes, dedicated circuits, panel
locations, terminations, testing/certification, and whether any existing firm alarm, security alarm,
CCTV/CATV, access control, audio/voting, or communications systems are to be modified,
relocated, protected, removed, reconnected, tested, or certified under this contract.
Response: Refer to “Section 2.1.5 Site Electrical”, “Section 2.1.6 Site Telephone and Data” and
“Section 2.1.7 Access Control System” for specifications, quantities, and testing requirements for
electrical, data, and low-voltage scope of work in this RFP. Refer to Exhibit ‘A’ for locations of
where electrical, data, and low-voltage items are to be placed in the proposed floor plan.
1B-6
Question: Please provide any asbestos, lead paint, or hazardous-material survey/reports
applicable to the Building 4 remodel area and the exterior concrete/step work areas. If no report
are available, please confirm that hazardous material testing, abatement, remediation, and
disposal are excluded from the base proposal and will be handled by the City or by change order
if encountered.
Response: The City has no asbestos, lead paint or hazardous materials survey reports to provide,
applicable to the Building 4 front counter remodel area and the exterior concrete steps work areas.
Refer to “Attachment B – General Conditions, Section 3.12 Hazardous Materials” for information
on hazardous materials testing, abatement, remediation and disposal requirements.
2
1B-7
Question: Please confirm allowed work hours, after-hours/weekend requirements, noise
restrictions, City Hall operational constraints, public/staff access requirements, temporary
barriers, dust control, pedestrian routing, staffing, parking, and whether City Hall services must
remain operational during construction.
Response: Refer to Attachment B General Conditions, Section 14.2 Hours of Work" for regular
work hours and requirements for performing work outside of regular work hours. Construction
noise is only permitted Monday through Saturday between 7:00 am and 7:00 pm unless expressly
approved by the Director of Engineering per the City of Santee Municipal Code. Refer to “Section
2.1.2 Construction Phasing” for temporary wall for noise and dust control, construction phasing,
and site accessibility requirements.
1B-8
Question: Please confirm the required demolition limits, subgrade preparation, base
requirements, concrete requirements, AC patch section, striping restoration handrail scope,
handrail finish, and inspection/testing requirements for the concrete step improvements at
Building 3, 4, and 6. Please also confirm whether unsuitable subgrade, unforeseen base repair,
or existing-conditions deficiencies will be handled by change order.
Response: Refer to “Section 2.1.11 Site Concrete Improvements” for specifications requirements
for demolitions, subgrade preparation, concrete, asphalt concrete, striping restoration, and
handrails scope of work for the exterior concrete steps. Refer to Exhibit ‘A’, sheets 8-11, for
required demolition limits, proposed concrete and asphalt concrete limits. If unforeseen conditions
are encountered during the work that requires additional work beyond the original scope of work,
it will be addressed through an amendment to the contract.
1B-9
Question: The drawings note that existing utility drawings may not show all utilities and identify
existing irrigation/control valves to be protected. Please provide available utility and irrigation as-
builts for the exterior work areas and confirm whether utility locating, potholing, rerouting, irrigation
modification, or repair of unknown/unmarked utilities is included in the base proposal or handled
by change order.
Response: See Attachment ‘E’ – City Hall Landscape As-Builts Drawings for existing landscape
irrigation at City Hall. No modifications or relocation of existing irrigation lines or valves are
anticipated for the concrete steps scope of work. The Selected Firm shall proceed with caution to
ensure that all utilities encountered, whether or not of record, shall be protected from damage.
Repairs to damaged utilities whether of record or not, shall be the Contractor’s responsibility at
no additional expense to the City.
Thank you,
Antonio Sandoval
Assistant Engineer
3
ATTACHMENT 'E'
Commodity Codes
  • NAICS 236220Commercial and Institutional Building Construction
* Disclaimer: Government BidHub provides information on bids, RFPs (Requests for Proposals), and RFQs (Requests for Qualifications) solely for convenience and informational purposes. This site is not an official public notice board. For official details, responses, or inquiries, please contact the relevant government agency directly.

Government Bids

Empower Your Bidding Strategy

Unlock Government BidHub's unparalleled access to high-quality, tailored bid information.

  • Access an extensive database of bids, including comprehensive local and state opportunities.
  • Receive customized alerts for the bids that matter most to your business.
  • Explore detailed specifications to ensure precise and competitive submissions.
  • Gain a competitive edge with up-to-date information and exclusive opportunities.

See Also

UW18030 MORMON SLOUGH SANITAR...

General Information Due Date: Thursday, July 9, 2026 Opening Time: 2:00 PM Published

City of Stockton

Bid Due: 7/09/2026

Specification No. 26-03, C516...

Specification No. 26-03, C51692, Spillway Maintenance, Pyramid DamDetails Event ID 0000039684 Format/Type: Sell

State Government of California

Bid Due: 7/22/2026