L1973 – CENTRAL GARAGE OPTIMIZATION RFQ
Project Information
- Bid Title
- L1973 – CENTRAL GARAGE OPTIMIZATION RFQ
- Issuing Agency
- The Massachusetts Port Authority (Massport)
- Location
- Massachusetts
- Published Date
- Apr 28, 2026
- Closing Date
- Jun 4, 2026
- Government Level
- State & Local
- Status
- Closed
- Ref. #
- L1973
- Original Source
- Join to Access Full Details
- Bid Inquiries
- Join to Access Full Details
- Bid Documents
- Join to Access Full Details
- Project Description
-
AdvertisedContract: L1973
L1973 – CENTRAL GARAGE OPTIMIZATION RFQ
Contract:
Opportunity Type:
L1973
Contractor/Vendor RFQ
If you would like to submit, please go to (BidExpress) .
Advertised Date:
Due Date:
04/29/2026 09:00:00 AM
06/04/2026 12:00:00 PM
- Attachment Preview
-
MASSACHUSETTS PORT AUTHORITYCAPITAL PROGRAMS DEPARTMENTSUITE 209S – LOGAN OFFICE CENTER SUITE 209SONE HARBORSIDE DRIVEEAST BOSTON MA 02128-2909REQUEST FOR QUALIFICATIONSL1973 – CENTRAL GARAGE OPTIMIZATIONLOGAN INTERNATIONAL AIRPORTSUPPLEMENTAL INFORMATION PACKAGEMPA CONTRACT NO. L1973APRIL, 2026LEGAL NOTICEREQUEST FOR QUALIFICATIONSThe MASSACHUSETTS PORT AUTHORITY (Authority) is soliciting consulting services for MPACONTRACT NO. L1973 – CENTRAL GARAGE OPTIMIZATION The Authority is seeking a qualifiedmultidiscipline consulting firm or team, with proven experience to provide professional services includingplanning, design, construction related services, including resident inspection relative to (1.) Central and WestGarage Operational Improvements and (2.) Structural Engineering Services associated with structuralrehabilitation of the Central and West Garages at Logan International Airport. The Consultant must be able towork closely with the Authority and other interested parties in order to provide such services in a timely andeffective manner.The consultant shall demonstrate experience in several disciplines including but not limited to Architectural(prime), Structural, Electrical, Plumbing, Geotechnical, Code Compliance, Cost Estimating, ConstructionPhasing, Climate Resiliency and Sustainable Design.The contract will be work order based, and that Consultant’s fee for each work order shall be negotiated;however, the total fee for the contract shall not exceed $15,000,000.A Supplemental Information Package will be available, on April 29, 2026 at 9:00 AM on the Capital BidOpportunities webpage of Massport http://www.massport.com/massport/business/bids-opportunities/capital-bids as an attachment to the original Legal Notice, and on COMMBUYS (www.commbuys.com) in the listingsfor this project. If you have problems finding it, please contact Susan Brace at Capital ProgramsSBrace@massport.com The Supplemental Information Package will provide detailed information about ScopeOf Work, Selection Criteria and Submission Requirements.In recognition of the unique nature of the project and the services required to support it, the Authority hasscheduled a Consultant Briefing to be held at 11:00 AM on May 7, 2026 via TEAMShttps://events.teams.microsoft.com/event/49059803-541a-48da-b9cc-8657ac3764ed@9eb9f7c2-9da5-4db8-aebc-3b74b4fadcbb. At this session, an overview of the project will be provided, the servicesrequested by the Authority will be described, and questions will be answeredBy responding to this solicitation, consultants agree to accept the terms and conditions of Massport’s standardwork order agreement. A copy of the Authority’s standard agreement can be found on the Authority’s web pageat http://www.massport.com/massport/business/capital-improvements/important-documents/. Consultant shallspecify in its cover letter that it has the ability to obtain requisite insurance coverage.This submission shall be addressed to Luciana Burdi, Intl. Assoc. AIA, CCM, MCPPO, NAC, FCMAAChief Infrastructure Officer and received no later than 12:00 Noon on June 4, 2026 Via Bid Expresshttps://www.bidexpress.com/businesses/27137/home. Any submission which is not received by thedeadline shall be rejected by the Authority as non-responsive.MASSACHUSETTS PORT AUTHORITYRichard A. DaveyCEO & EXECUTIVE DIRECTOR1REV: 05-14-2025BackgroundThe Central Garage is one of twostructures, together with the WestGarage, that comprise the AirportCentral Parking Facility. The mainvehicular entrance to the CentralGarage is through Level 1 of the WestGarage. The precast concrete CentralGarage structure consists of eight levels,which are labeled G, 1, 2, 3, 4, 5, 6 and7. The Central Garage is connected tothe West Garage by nine bridges, twobridges on Levels 3 and 4, and onebridge on each of Levels 1, 2, 5, 6 and7. Vehicles may leave the CentralGarage by crossing any bridge to theWest Garage (although garage signagedirects vehicles to the Central Garage’sLevel 2 to exit). Vehicles within the West Garage may use a helical ramp at Level 2 to exit. All structuresassociated with fee collection for the West and Central Garages are located within the West Garage.The Central Garage has a parking capacity of approximately 7,000 cars that is open to the public 24 hoursper day, seven days per week. Additionally, there is an entrance accessible to the public for parkingpurposes via the Arrivals roadway opposite Terminal C, as well as one entering the Central Garage on itsnorth face. The vertical clearance of the Central Garage is designated as 6’-10”.The Ground Level has served as a rideshare pickup/drop-off since October of 2019. As part of Massport’sTNC (Transportation Network Companies) initiatives, further modifications to the garage have since beenmade to increase flow through the Ground Level with several additional points of access/egress opened inthe façade.HistoryThe original Central Garage was constructed in1966 and included a ground level, anintermediate level and a roof level. In 1969 twoadditional deck levels were added to the originalgarage, Level 4 and Level 5, with Level 5becoming the new roof. During the early yearsof the Central Garage, all ticket dispensing andtoll collection took place outside the garage atthe main entrance west of the garage. In 1970the construction of the Air Traffic Control(ATC) Tower was completed and a portion ofthe garage was removed. In the center east faceof the garage a 200 foot wide and 65-foot-deep section of the Central Garage wasremoved for the placement and construction ofthe ATC Tower. Later the area between the2REV: 05-14-2025tower and the garage was enclosed bya Level 3 deck and intermediate levelconcrete beams on the first and secondlevel. In 1998, the Central Garage tollplaza was removed and replaced witha seven level West Garage. At thistime the Central Garage’s five parkinglevels were re-named to match theparking levels in the West Garage.The Central Garage’s lowest level wasdesignated Level G, the next level wasrenamed Level 1 with Level 4becoming the new roof level.In 2007, a vertical expansion projectfor the Central Garage wascompleted. This expansion included three additional parking deck levels constructed on top of theexisting Central Garage, a new exterior façade, new elevators, new stairwells, the replacement of the 1966Double-Tee beams on the two lowest parking decks, improved signage and graphics, and improvedpedestrian circulation with all pedestrian transfers at Level 4. The effort to add three decks on top of theexisting Central Garage required internal and external columns to be placed in and around the existingCentral Garage. The new exterior columns were the framework for the new façade and allowed closurepanels/decks to be installed to the existing lower decks. The new internal columns are supported onpiles and pass through holes in the existing parking levels to support the new decks above. The differencein deck elevations for the existing parking levels is approximately 10 feet and the three additional deckshave a difference in elevation of 12 feet from level to level. The northeast and southeast stairwells havethree elevators, a lobby on each floor and a Level 4 pedestrian connection via bridges to Terminals A, Band C.ConstructionThe layout of the Central Garage isrectangular, approximately 750 feet by 500feet, with its major axis running north-south.The Central Garage building grid/column linesare numbered from north to south as 1 through30 and are labeled alphabetically from east towest as A through J. The structure’s originalcolumns are generally located on the wholenumber gridlines and the upper-level additioncolumns are located at intermediate gridlines.For Levels 1, 2, 5, 6, and 7, the parking structureis supported by a network of Inverted-Teeconventionally reinforced concrete girders andDouble-Tee prestressed concrete beams. Themain girders/Inverted-Tees run north and south along the alphabetized column lines of the garage. TheDouble-Tee beams run east to west and are supported on the main girders with the stem of the Double-Tee cast with a dapped end where they bear on the main girder. The support girders on deck Levels 3and 4, which consist of the original girders installed in 1969, are segmented girders consisting of a top3REV: 05-14-2025flange and two rectangular concrete stemslinked by concrete diaphragms oppositehaunches that extend beyond the outside of thegirder to act as bearing seats for the Double-Teebeams.The garage façade, constructed after 2007, hasclosure panels that linked the older decks withthe outer façade. In the upper levelsconstructed after 2007, the decks extenddirectly to the spandrel beams of the newfaçade. On the spandrel beams there arehaunches that provide support for the Double-Tee beam against the façade.In the center of the structure, there are rampsthat provide vehicular access from level to level. There are two ramps on each level providing a counter-clockwise circulation for vehicles to move up and a clockwise circulation to move down a level. FromLevel G to Level 3, the ramps have a slope of approximately 5.5% and a width of 12 feet between theirparapet walls. From Level 4 to the roof, the ramps have a slope of approximately 6.6% and a width of 16’3” between their parapet walls. The ramp vertical clearances for Level G to Level 3 are 7’-3” and for Level4 to Level 7 are 8’-6”.Expansion joints in the deck are configured differently at each level. Levels 1 and 2 have expansion jointson Column Lines 5, 9, 13, 15.5, 18, 22 and 26. Level 3 has expansion joints on Column Lines 5, 9, 13,15.5, 18, 22, 26, E and G. Level 4 has expansion joints on Column Lines 5, 9, 13, 15.5, 18, 22, 26, C, Eand G. Levels 5 and 6 have expansion joints on Column Line 15.5. Level 7 has expansion joints onColumn Lines 7.5, 15.5, 23.5, and E.The Central Garage has a stairwell and an elevator at each quadrant of the parking levels. The northwestand southwest quadrants of the garage each contain a single elevator and a stairwell. The northeast andsoutheast stairwells each contain multiple elevators and are connected to adjoining pedestrian bridgesconnecting to Terminals A, B and C at Level 4.Condition Assessment and Recent Repair WorkA structural condition assessment of the Central Garage wascompleted in 2024. Recommendations from that report ranged from:• Rehabilitation of the drainage system for the garage.• Rehabilitation of many of the structural elements of thegarage, including:o Repairs to girders;o Repairs to columns;o Repairs to beams;o Repairs to decks (in particular, the decks on Levels3 and 4);o Repairs to expansion joints;4REV: 05-14-2025
Empower Your Bidding Strategy
Unlock Government BidHub's unparalleled access to high-quality, tailored bid information.
- Access an extensive database of bids, including comprehensive local and state opportunities.
- Receive customized alerts for the bids that matter most to your business.
- Explore detailed specifications to ensure precise and competitive submissions.
- Gain a competitive edge with up-to-date information and exclusive opportunities.
See Also
Header Information Bid Number: BD-26-1454-CONT1-CONT1-130968 Description: RFQ for Route 60 Redesign Bid Opening
Commonwealth of Massachusetts
Bid Due: 7/17/2026
Bid Title: RFQ for Route 60 Redesign Category: Bids and Request for Proposals
City of Malden
Bid Due: 7/17/2026