SPECIFICATIONS
FOR
EV Charging Facility
200 S. Merchant Street
PREPARED BY
JEREMY HEUERMAN, P.E.
DIRECTOR OF PUBLIC WORKS
201 EAST JEFFERSON AVENUE
P.O. BOX 648
EFFINGHAM, ILLINOIS
February 2026
1
Contents
NOTICE TO CONTRACTORS............................................................................................................................ 3
SPECIAL PROVISIONS..................................................................................................................................... 4
SCOPE OF WORK........................................................................................................................................ 4
PAYMENT AND PERFORMANCE BOND ...................................................................................................... 4
LIQUIDATED DAMAGES.............................................................................................................................. 4
PREVAILING WAGE..................................................................................................................................... 5
SUBSTANCE ABUSE AND PREVENTION PROGRAM.................................................................................... 5
INSURANCE................................................................................................................................................ 5
CONTRACTOR RESPONSIBLE FOR LOCATING AND MAINTAINING UTILITES .............................................. 6
PORTLAND CEMENT CONCRETE PAVEMENT ............................................................................................. 7
GRADING AND SUBGRADE PREPARATION FOR CONCRETE ITEMS ............................................................ 7
CONTRACT..................................................................................................................................................... 9
PROPOSAL ................................................................................................................................................... 11
REFERENCES ............................................................................................................................................ 12
BID PRICE ................................................................................................................................................. 13
NOTICE OF AWARD...................................................................................................................................... 15
NOTICE TO PROCEED................................................................................................................................... 16
2
SPECIAL PROVISIONS
The following Special Provisions supplement the “Standard Specifications for Road and Bridge
Construction of the State of Illinois”, adopted January 1, 2022, which govern the EV Charging Facility
Project, City of Effingham, Illinois, and in case of conflict with any contract documents, Article 105.05
shall apply.
SCOPE OF WORK
The work included in this project consists of the fully energized installation of electrical and conduit work
for a proposed EV Charging Station base plate, a second future EV Charging Station base plate with
conduit and DC pairing wiring, concrete parking lot, sidewalks and other miscellaneous work in
conjunction with this project at 200 S. Merchant Street.
PAYMENT AND PERFORMANCE BOND
Section 102 of the Standard Specifications for Road and Bridge Construction shall be revised as follows:
The Contractor shall deliver a payment and performance bond to the City Clerk in the total amount of
the contract at the time the contract is executed by the City.
Such bond shall be conditioned for the completion of the contract, for the payment of material used in
such work and for all labor performed in such work, whether by subcontractor or otherwise.
Each such bond is deemed to contain the following provisions whether such provisions are inserted in
such bond or not:
“The principal and sureties on this bond agree that all the undertakings, covenants, terms, conditions
and agreements of the contract or contracts entered into between the principal and the City will be
performed and fulfilled and to pay all persons, firms and corporations having contracts with the principal
or with subcontractors, all just claims due them under the provisions of such contracts for labor
performed or materials furnished in the performance of the contract on account of which this bond is
given, when such claims are not satisfied out of the contract price of the contract on account of which
this bond is given, after final settlement between the City and the principal has been made.”
The bond required by this Section may be acquired from an Illinois company, agent or broker of the
contractor’s choice, except that the bond supplier shall be rated A (Excellent) or A+ (Superior), Financial
Size Category Class XII or larger, in the most recent issue of Best’s Key Rating Guide published by A.M.
Best Company of Old wick, New Jersey 08858.
FOR ALL CONTRACTS UNDER $100,000, a bank letter of credit from a local (Effingham County) bank
setting forth all of the conditions herein before stated and signed and attested to by two officers of said
bank and the Contractor shall be considered to be acceptable under this section.
LIQUIDATED DAMAGES
It is understood and agreed that time is of the essence in the performance of the Contract and that
failure on the part of the Contractor to complete the contract work in the time herein set forth will result
4
in certain loss and damages to the Owner. Failure on the contractor’s part to complete such work shall
be considered just cause for forfeit of his/her surety bond.
In case the Contractor of the work shall fail or neglect to complete any section of work on or before July
1, 2026, then said Contractor shall and will pay to the Owner such sums as may be due to him under the
terms of the Contract at the rate specified in the Standard Specifications for Road and Bridge
Construction adopted January 1, 2022.
PREVAILING WAGE
The prevailing rate of wages ascertained by the Illinois Department of Labor (IDOL) or as determined by
the court on review shall be paid to all laborers, workers, and mechanics performing work under this
contract pursuant to Public Act 100-1177. The prevailing rate of wages are revised by IDOL and are
available on the Department's official website. Any revised rate shall apply to this contract, and the
contractor shall be responsible to pay the revised rate. The contractor shall be responsible for
determining the appropriate rates for this project and for anticipating the prevailing wage rate that will
apply at the time the work is performed. The contractor shall be responsible for submitting all certified
payrolls for the awarded project and for any subcontractor work to the IDOL website pursuant to Public
Act 100-1177. Paper or electronic copies shall be provided to the City upon request for up to 3 years
after the project is complete.
SUBSTANCE ABUSE AND PREVENTION PROGRAM
In addition to all other labor requirements set forth in this proposal and in the Standard Specifications
for Road and Bridge Construction, adopted by the Department, during the performance of this contract,
the Contractor for itself, its assignees, and successors in interest (hereinafter referred to as the
“Contractor”) agrees as follows:
Before the Contractor and any Subcontractor commences work, the Contractor and any Subcontractor
shall have in place a written Substance Abuse Prevention Program for the prevention of substance abuse
among its employees which meets or exceeds the requirements in P.A. 95-0635 or shall have a collective
bargaining agreement in effect dealing with the subject matter of P.A. 95-0635. The Contractor and any
Subcontractor shall file with a public body: a copy of the substance abuse prevention program along with
a cover letter certifying that their program meets the requirements of the Act, or a letter certifying that
the Contractor or a Subcontractor has a collective bargaining agreement in effect dealing with the
subject matter of this Act.
INSURANCE
Contractors are required to furnish the City with Certificates of Insurance in the following amounts and
the City of Effingham will be listed as an Additional Insured on a primary non-contributory basis. The
Certificate of Insurance shall be accompanied by an “Additional Insured – Designated Person or
Organization” form.
Worker’s Compensation
Employer’s Liability
General Liability
Auto Liability
Excess Liability
Statutory Limits
$ 1,000,000
$ 2,000,000
$ 1,000,000
$ 2,000,000
5
Commodity Codes
  • NAICS 541330Engineering Services
* Disclaimer: Government BidHub provides information on bids, RFPs (Requests for Proposals), and RFQs (Requests for Qualifications) solely for convenience and informational purposes. This site is not an official public notice board. For official details, responses, or inquiries, please contact the relevant government agency directly.

Government Bids

Empower Your Bidding Strategy

Unlock Government BidHub's unparalleled access to high-quality, tailored bid information.

  • Access an extensive database of bids, including comprehensive local and state opportunities.
  • Receive customized alerts for the bids that matter most to your business.
  • Explore detailed specifications to ensure precise and competitive submissions.
  • Gain a competitive edge with up-to-date information and exclusive opportunities.

See Also

509 PARKING GARAGE RAILING RE...

BUYER: Sara Rogers (email for Bid Document) EMAIL: sara.rogers@dupagecounty.gov NOTICE TO BIDDERS NOTICE

DuPage County

Bid Due: 7/23/2026

Renovate Building/Upgrade Bui...

Project 624-060-045 Bid Date Tuesday, July 07, 2026 11:00 AM Description Renovate Building/Upgrade

Illinois Capital Development Board

Bid Due: 7/07/2026