Request for Quotations-Torringford School Replacement Chiller and Commissioning Services Addendum No. 1
Project Information
- Bid Title
- Request for Quotations-Torringford School Replacement Chiller and Commissioning Services Addendum No. 1
- Issuing Agency
- Torrington Public School
- Location
- Connecticut
- Published Date
- Jun 4, 2026
- Closing Date
- Jun 9, 2026
- Government Level
- State & Local
- Status
- Closed
- Original Source
- Join to Access Full Details
- Bid Inquiries
- Join to Access Full Details
- Bid Documents
- Join to Access Full Details
- Project Description
- Attachment Preview
-
ADDENDUM NO. 1Project: Torrington Board of Education—REQUEST FOR QUOTATIONS FOR TORRINGFORDELEMENTARY SCHOOL AIR-COOLED SCREW CHILLER REPLACEMENTPurpose of this Addendum The purpose of this document is to answer requests for information, provideExhibit F, remove the heat trace tape from the bid to owner responsibility, clarify the amount of butterflyvalves, and clarify the BMS system responsibilities.1. Requests for Information (RFI) Answers● Question: Is a DAS prequalification certificate and bid statement required? Answer: No.● Question: What is the retainage? Answer: 5% of each progress payment.● Question: Are we required to provide preventative maintenance once the job is done? If so, forhow long? This would be separate from our 1-Year Workmanship Warranty. Answer: Notrequired.● Question: Under Commissioning and start up: System Flushing: Confirming the water loop wasproperly flushed to prevent debris from clogging the chiller's heat exchangers. Typically this isdone for new systems unless there are existing issues. This could increase the cost. Can this beadded as an add on? Answer: Every component of the water loop and interconnected systemsaccessed or impacted during this replacement—including all new piping, isolation valves, and theboiler room's hydraulic assembly—must be properly flushed. This ensures the entire system isclear of debris before the new chiller is commissioned to prevent clogging the heat exchangers.2. Scope of Work Clarifications & Changes● Valve Clarification: The contractor must furnish and install two (2) new gear-driven butterflyvalves for isolation on the lines going to the chiller unit barrel.● Scope Removal: Remove from the scope of work: furnish and install new self-regulating heattrace tape on the outside supply and return lines to the chiller unit barrel.3. BMS System ClarificationOwner's/SNE BMS Responsibility:● To provide a BACnet connection to the chiller.● All low-voltage electrical work for the BMS connection.● All programming and interfacing with the chiller and graphics.● Provide startup assistance to the chiller manufacturer.The RFQ bid shall include:● Flow switches installed. Wired by SNE.● BACnet card provided by manufacturer—interface connection by SNE.● All coordination with SNE.4. Exhibits● Exhibit F: Provided (Form of Contract).DESIGN-BUILD AGREEMENT AND GENERAL CONDITIONSBETWEEN OWNER AND DESIGN-BUILDERTABLE OF ARTICLES1. AGREEMENT2. GENERAL PROVISIONS3. DESIGN-BUILDER’S RESPONSIBILITIES4. OWNER’S RESPONSIBILITIES5. SUBCONTRACTS6. CONTRACT TIME7. CONTRACT PRICE8. CHANGES IN THE WORK9. PAYMENT10. INDEMNITY, INSURANCE, AND BONDS11. SUSPENSION, NOTICE TO CURE, AND TERMINATION12. DISPUTE MITIGATION OR RESOLUTION13. MISCELLANEOUS14. CONTRACT DOCUMENTSARTICLE 1 AGREEMENTThis Agreement (“Agreement”) is made this [___] day of [MONTH] in the year 2026 (“Effective Date”) by and between theOWNER (“Owner”): TORRINGTON BOARD OF EDUCATION50 MAJOR BESSE DRIVETORRINGTON, CT 06790and theDESIGN-BUILDER (“Design-Builder”): [NAME][ADDRESS]for services in connection with the followingPROJECT: Turnkey design, construction and installation, commissioning and start-up by Design-Builder of and for a newair-cooled screw chiller unit (the “Chiller Unit”) for the Torringford Elementary School building (“Facility”), at theWorksite(as defined in Section 2.4.28) located 800 Charles Street, Torrington, CT 06790 (the “Property”).ARTICLE 2 GENERAL PROVISIONS2.1. TEAM RELATIONSHIP Design-Builder and Owner agree to proceed with the Project on the basis of trust, good faith,and fair dealing. Design-Builder agrees to furnish or procure, as permitted by Applicable Law, the architectural andengineering services set forth in this Agreement and the construction and administration of the Work.2.1.1. Neither Design-Builder nor any of its agents, employees, or Subcontractors, shall act on behalf of or in the name ofOwner unless authorized in writing by Owner’s Representative.2.2. ETHICS The Parties shall perform their obligations under this Agreement with integrity, and shall, at a minimum: (a)avoid conflicts of interest; (b) promptly disclose to the other Party any conflicts of interest which may arise. Each Partywarrants that it has not and shall neither pay nor receive any contingent fees or gratuities to or from the other Party, includingits agents, officers and employees, Design Professional, Subcontractors, Sub-subcontractors, Suppliers or SeparateContractors, or others for whose acts or omissions they may be liable, to secure preferential treatment.12.3. DESIGN PROFESSIONAL Architectural and engineering services shall be provided or procured by licensed,independent design professionals retained by Design-Builder, or furnished by licensed employees of Design-Builder, aspermitted by Applicable Law. The person(s) or entity(ies) providing architectural and/or engineering services shall bereferred to in this Agreement, collectively, as “Design Professional.” If a Design Professional is an independent designprofessional, the architectural services and/or engineering services shall be procured pursuant to a separate written agreementbetween Design-Builder and Design Professional.2.3.1. STANDARD OF CARE Design Professional shall furnish and provide the architectural services and/orengineering services necessary to design the Project in accordance with Owner’s requirements, as outlined in Owner’sProgram and other relevant data defining the Project. The architectural services and/or engineering services shall beperformed in accordance with the standard of professional skill and care required for a Project of similar size, scope, andcomplexity, during the time in which the Services are provided.2.4. DEFINITIONS2.4.1. “Agencies” or an “Agency” mean and include the Connecticut Office of Policy and Management (“OPM”), theConnecticut Commission on Human Rights and Opportunities (“CHRO”), and all other governmental authorities havingregulatory or administrative jurisdiction over the Work and/or the Project, and all representatives or designees of DAS,CHRO, and such other governmental authorities.2.4.2. “Agreement” means this Design-Build Agreement and General Conditions Between Owner and Design-Builder,amendments, exhibits, addenda, and attachments made part of this Agreement upon its execution and/or upon theexecution of any amendment to this Agreement.2.4.3. “Applicable Law” and “Applicable Laws” mean and include all federal, state, and local laws, statutes, regulations,ordinances, codes, building codes, rules, and/or permits, and lawful orders enacted, promulgated or issued by anygovernmental body or public or quasi-public authority having jurisdiction over the Work, Design-Builder, and/or the siteof the Project that are applicable to the Work, and with which Design-Builder must comply. “Applicable Law” shallinclude, without limitation, those relating to equal opportunity, labor, wages and employment laws, statutes, ordinances,codes, rules and regulations, and all guidelines, standards and conditions of funding imposed on the Work and/or Projectby the Agencies or otherwise applicable to the Project, the Agreement, any Subcontract and/or the performance of theWork.2.4.4. “Business Day” means all days, except weekends and official federal or state holidays where the Project is located.2.4.5. A “Change Order” is a written order signed by Owner and Design-Builder after execution of this Agreement,indicating changes in the scope of the Work or Contract Time, including substitutions proposed by Design-Builder andaccepted by Owner.2.4.6. “Construction Schedule” is the document prepared by Design-Builder that specifies the dates on whichDesign-Builder plans to begin and complete various parts of the construction phase services Work, and the Project,including dates on which information and approvals are required from Owner.2.4.7. The “Contract Documents” consist of those documents identified in section 14.1.2.4.8. The “Contract Time” is the period of time beginning on and including the Date of Commencement through thetotal time within which Design-Builder is required to achieve Substantial Completion established in Section 6.2.2.4.9. “Day” and “day” mean calendar day.2.4.10. “Date of Commencement” is as provided for in section 6.1.2.4.11. “Defective Work” is any portion of the Work that is not in substantial conformance with the requirements of theContract Documents.2.4.12. “Final Completion” occurs on the date when Design-Builder’s obligations under this Agreement are completeand accepted by Owner, and final payment becomes due and payable.2 2.4.12.1 “Final Completion Time” is period of time beginning on the Date of Substantial Completion through thetotal time within which Design-Builder is required to achieve Final Completion established in Section 6.2.2.4.13. “Hazardous Material” means and includes a substance or material identified now or in the future as hazardousunder any Applicable Laws, or any other substance or material which is considered hazardous or otherwise subject tostatutory or regulatory requirements governing handling, disposal or clean-up. “Hazardous Material” does not mean orinclude any substance or material that is specified or foreseeably required to be removed, disposed of, or used as part ofor in the performance of the Work by Design-Builder notwithstanding that such substance or material is otherwiseidentified as hazardous under Applicable Laws, is considered hazardous, or is otherwise subject to statutory or regulatoryrequirements governing handling, disposal or clean-up.2.4.14. “Construction Change Directive” is any written order containing Work instructions directed by Owner forchanges to the scope of the Work required to performed or provided by Design-Builder pursuant to this Agreement,which is signed by Owner after execution of this Agreement and before Substantial Completion of the Work.2.4.15. “Separate Contractors” means other contractors engaged by Owner performing construction work or providingconstruction services at the Project site as part of the Project, other than Design-Builder, its Subcontractors, and itsSuppliers.2.4.16. “Overhead” shall mean (a) payroll costs and other compensation of Design-Builder’s employees inDesign-Builder’s principal and branch offices; (b) general and administrative expenses of Design-Builder’s principal andbranch offices including charges against Design-Builder for delinquent payments; and (c) Design-Builder’s capitalexpenses, including interest on capital used for the Work.2.4.17. The “Owner” is the person or entity identified in ARTICLE 1 and includes Owner’s representative(s).2.4.18. The “Owner’s Program” is a description of Owner’s objectives, budgetary and time criteria, space requirementsand relationships, and if applicable to the Project, flexibility and expandability requirements, special equipment andsystems, and site requirements. The Owner’s Program may include preliminary Design Documents which shall includedrawings, and may include outline specifications and other conceptual documents illustrating the Project’s basicelements, scale, and their relationship to the Worksite.2.4.19. The “Parties” are collectively Owner and Design-Builder.2.4.20. The “Project,” as identified in ARTICLE 1, is the facility and other improvements for which Design-Builder is toperform the Work under this Agreement. The Project may also include improvements to be undertaken by Owner orSeparate Contractors.2.4.21. “Project Schedule” A schedule that shows the timing and sequencing of the design and construction required tomeet the time criteria set forth in the Owner’s Program. The Project includes the Construction Schedule and iscoordinated with design phase service activities.2.4.22. A “Subcontractor” is a person or entity retained by Design-Builder as an independent contractor to provide thelabor, materials, equipment, or services necessary to complete a specific portion of the Work. The term Subcontractordoes not include the Design Professional, or any Separate Contractor employed by Owner or any Separate Contractor’ssubcontractors.2.4.23. “Substantial Completion” of the Work occurs on the date when construction is sufficiently complete inaccordance with the Contract Documents so that Owner can occupy or utilize the Project for the use for which it isintended, without unscheduled disruption. The date on which Substantial Completion is achieved shall be the date setforth in and confirmed in and through a certificate of Substantial Completion signed by Owner and Design-Builder (the“Date of Substantial Completion”). The certificate shall state the respective responsibilities of Owner andDesign-Builder for security, maintenance, heat, utilities, damage to the Work, and insurance. The certificate shall also listthe items to be completed or corrected by Design-Builder, and establish the time for completion and correction of suchitems within the timeframe, if any, established in subsection 6.2.3 for the Final Completion Time.2.4.24. A “Sub-subcontractor” is a party or entity who has an agreement with a Subcontractor or otherSub-subcontractor, or Supplier to perform any portion of the Work or to supply material or equipment as part of theWork.3
- Commodity Codes
-
- NAICS 238220Plumbing, Heating, and Air-Conditioning Contractors
- NAICS 541330Engineering Services
* Disclaimer: Government BidHub provides information on bids, RFPs (Requests for Proposals), and RFQs (Requests for Qualifications) solely for convenience and informational purposes. This site is not an official public notice board. For official details, responses, or inquiries, please contact the relevant government agency directly.
Empower Your Bidding Strategy
Unlock Government BidHub's unparalleled access to high-quality, tailored bid information.
- Access an extensive database of bids, including comprehensive local and state opportunities.
- Receive customized alerts for the bids that matter most to your business.
- Explore detailed specifications to ensure precise and competitive submissions.
- Gain a competitive edge with up-to-date information and exclusive opportunities.
See Also
Civil Engineering Design and ...
Project ID: Title: Civil Engineering Design and Construction Administration Services for Timberlin Golf
Town of Berlin
Bid Due: 7/23/2026
Comprehensive Downtown Parkin...
Project ID: Title: Comprehensive Downtown Parking Study & Management Plan RFQ Addenda: 0
City of Shelton
Bid Due: 7/24/2026