54th Ave. North Force Main Replacement (PID 005584B)
Project Information
- Bid Title
- 54th Ave. North Force Main Replacement (PID 005584B)
- Issuing Agency
- Pinellas County
- Location
- Florida
- Published Date
- Apr 9, 2026
- Closing Date
- Apr 28, 2026
- Government Level
- State & Local
- Status
- Closed
- Ref. #
- 26-0359-ITB-C
- Original Source
- Join to Access Full Details
- Bid Inquiries
- Join to Access Full Details
- Bid Documents
- Join to Access Full Details
- Project Description
-
Project ID: 26-0359-ITB-C
Title: 54th Ave. North Force Main Replacement (PID 005584B)
Addenda: 0
Release Date: 4/9/2026
Due Date: 4/28/2026
54th Ave. North Force Main Replacement (PID 005584B)FollowInvitation to Bid - Construction (ITB-C)PUBLIC WORKS03196 , 21015 , 21035 , 65846 , 72064 ... show allProject ID: 26-0359-ITB-CRelease Date: Thursday, April 9, 2026· Due Date: Tuesday, April 28, 2026 3:00pmPosted Thursday, April 9, 2026 8:00amAll dates & times in Eastern TimeDraft Response No Bid18 days, 17 hours, 41 minutesOverview
Post Information
Posted At:Thu, Apr 9, 2026 8:00 AM
Sealed Bid Process:Yes (Bids Sealed / Pricing Sealed)
Private Bid:No
SummaryPinellas County is undertaking the replacement of an existing force main along 54th Avenue North, extending from the west side of St. Joes Creek to 74th Street North, then tying-in to the existing 36” force main at the South Cross Bayou Water Reclamation Facility. The project involves replacing approximately 1137 linear feet (LF) of an existing 24-inch prestressed concrete cylinder pipe (PCCP) force main due to compromised conditions downstream of the project site. The existing downstream force main has ruptured twice, resulting in sewage spills. Due to those past pipe failures, the force main within 54th Avenue North is being replaced as a preventative measure.
BackgroundThe proposed replacement pipe consists of approximately 1165 LF of 24-inch PVC pipe (C-900), which will be a combination of standard PVC pipe, fusible PVC pipe, and restrained joint pipe. The new force main connects to the existing 24-inch PVC force main located on 54th Avenue North, approximately 175 feet west of St. Joes Creek. The force main then extends west along 54th Avenue North then north along to 74th 27 Street North, where it connects to an existing 36-inch PVC force main approximately 720 feet north of 54th 29 Avenue North. Installation of the proposed force main will involve a combination of open-cut trenching and horizontal directional drilling. Additionally, a series of air valves will be installed along the proposed force main to ensure efficient operation. This project also includes the restoration of impacted areas within the project limits, restoring the conditions in these areas to their state prior to construction. Restoration includes, but is not limited to, landscaping of impacted areas, as well as road milling and paving.
Timeline
Issue Date:April 9, 2026Step 1 Question Submission Deadline:April 17, 2026, 3:00pmStep 1 Bid Qualification Submission Deadline:April 28, 2026, 3:00pmStep 2 Bid Submission Deadline:May 12, 2026, 3:00pm - Commodity Codes
-
- NAICS 237110Water and Sewer Line and Related Structures Construction
Empower Your Bidding Strategy
Unlock Government BidHub's unparalleled access to high-quality, tailored bid information.
- Access an extensive database of bids, including comprehensive local and state opportunities.
- Receive customized alerts for the bids that matter most to your business.
- Explore detailed specifications to ensure precise and competitive submissions.
- Gain a competitive edge with up-to-date information and exclusive opportunities.
See Also
Orange County Corrections Dep...
Project ID: Y25-790-RC Title: Orange County Corrections Department Female Detention Center Two Cell
Orange County
Bid Due: 7/14/2026
Project: Deerfield Island ADA Dock Ref. #: PNC2132293C1 Department: FASD - Purchasing Type:
Broward County
Bid Due: 7/15/2026